Thursday 4th September
Almost all of the team attended on what initially looked like it would be the wettest day we have worked for a long time.
Ian,
Martin and Jonathan took on the completion of the clearance of the down side low
mileage toe ditch at the River Isbourne bridge (21A). This is the
ditch that runs alongside the Winchcombe Industrial estate, with
Winchcombe Reclamation being the immediate adjoining premises. They
finished the vegetation clearance right up to the B4632 main road.
This revealed an old gate from the roadside, however it is
immediately above the ditch, so of no use for access with mechanical
plant. The group cleared the two sections of ditch that was obstructed
with soil; and also removed an obstruction at the end of the (non
railway) culvert that runs under the B4632 road. The result of this
was that water began to flow down
the ditch, although
slowly. Apart
from the River Isbourne, this was the only flowing water the team
encountered today.The old gate is just visible above where the toe ditch ends. [Photo by Jonathan] With the exit from the culvert under the road cleared, water begins flowing down the ditch. [Photo by Jonathan]
Ian (l) and Martin showing how shallow the River Isbourne still is. [Photo by Jonathan] |
An afternoon task was the cataloguing of our stock of tubes for the manufacture of safety rails and markers. Some of this is bespoke handrail tube, but most of recycled scaffold poles.
The
other seven attendees undertook
the culvert and cross drain visual inspections and clearance for the
day. They travelled
north to Little Buckland; where they split into to teams.
Dave, Nigel and
Peter headed south to deal
with
cross drains 5D and
6A at Laverton; also clearing
the up side toe
drain chambers north of bridge 6. Nigel on the brushcutter clears around the 6A exit chamber whilst Peter removes a sapling with the loppers. [Photo by Dave]
The end result - chamber lids exposed and access cleared.
Roger, John, Polly and Andrew
headed north to Peasebrook to attend to cross drain 3A. On the way
they cleared around the now disused field access on the down side –
this to ensure we can safely turn our vehicles here.
This reduces the distance
travelled in reverse between Little Buckland and Peasebrook. Next
item for clearing was the length of the down side toe ditch between
cross drain 5B and the northern most
foot crossing. Even
after the rain over the past few days; there was no water in this
ditch.Adhering to our confined spaces procedure, Roger enters the exit chamber of 3A whilst John holds the gas detection unit. John tidying around the down side of the northern most foot crossing at Little Buckland.
All
seven then met up at Meadow Lane
bridge for lunch –
slightly extended to
await the passing of a short but
heavy shower of rain. After lunch the final structure for clearing
and inspecting was the syphon cross drain 6C, which is just north of
Stanton
Fields bridge (7).The inspection and clearing team (well 5 out of the 7) finish off and start packing up at 6C. Stanton Fields bridge 7 in background.
Wildlife report:
No interesting
mammal sightings today. At Little Buckland we noted a buzzard hunting
over the adjacent field, so probably there are some small mammals
there. The work at Stanton Fields disturbed a family of crows. The
most numerous creatures we encountered were
arachnids. Every
chamber we inspected
seemed to have a
resident spider or
two. Apologies to anyone suffering from Arachnophobia.
Maybe the reason that even after the rain over the past few days there was no water in the ditches is that the ground is so dry that most/all of the falling water is soaked up. Only once the ground is damp will runoff resume.
ReplyDelete