Thursday 29th January
The only plus point for today’s weather report was that it did not rain. However, for most of the day it was misty, grey and with a keen wind blowing. Even the canopy on platform 1 at Toddington provided no shelter. It is certainly still winter. The warmest spot was inside the toilet block!
Eight of the team endured the cold at Toddington. A ninth member, Jonathan, attended dumper and mini-digger re-certification at Winchcombe.
The work at Toddington was to progress the improvements to the drainage of the down side cutting on the low mileage side of Stowe Road bridge. Polly constructed a low training wall by the adjacent cess chamber, Ian and Nigel acted as hod carriers and mortar mixers keeping him supplied with bricks and mortar. The first task for the others in the team (Dave, Roger, John, Andrew, Peter) was to remove some cut vegetation from the cutting side. This was medium size branches, which required a chain gang to carry them up the steep slope to the growing pile on the top. With that cleared, Dave and Roger brush cut the cutting side, as far as the course of the existing field drain. Meanwhile, the other three began removing the vegetation around the fencing at the top of the cutting. The fence here is in very poor condition, so we will replace it as the last item on this job. The small section of roadside fence was removed (mainly the very rusty remains of a gate) and replaced with temporary heras fence panels.
| Nigel and Polly building the training wall. |
| Cleared fence line by the roadside with temporary heras panels in place. |
| Roger and Dave finish off brush cutting the cutting side. |
After lunch the main tasks included the removal of a tree stump a third of the way up the cutting side, and excavation around the end of the existing land drain. Unfortunately a rummage through our stock of pipes and connectors at Winchcombe first thing in the morning did not reveal any of the correct size. So working on the ‘measure twice, cut once’ principle we took some more measurements on site. Particularity for the extension of the field drain, as this involves an imperial SGP to metric plastic twinwall convertor. Last task of the afternoon was to point up the new brickwork and to cover with some plastic sheeting to keep the rain off whilst the mortar dries.
| Stumped! Peter and Ian wrestle with the tree stump, whilst Nigel is ready to prevent any collisions with the new new wall. Polly in the background carries on with pointing up. |
| Ian digs around the exit of the existing land drain. The temporary pipe we inserted last week is not quite the correct diameter to avoid all leakage. |
| End of day with the new training wall covered. Height and position of the blue mesh chamber cover is only temporary. |
Whilst at Toddington, Ian knocked off one outstanding small task by removing the stump of a telegraph pole stay in the hedge just on the high mileage side of the Platform 2 entrance gate. We know of only one other remaining pole stay stump on the line, but that has small tree growing around it.
Wildlife report: Another species of bird to add to our list of observations was a wren. The hedges of the station and nearby cottages at Toddington providing a suitable habitat. In the adjoining fields north of the station we observed a large flock of crows, a few gulls and a red kite. On the way back to Winchcombe we noted a kestrel, so getting the raptor count to two. The mammal count was zero, unless we count a black and white domestic cat who passed by the entrance to Churchward House to the gaps between the containers in the yard. No doubt performing a useful service to the railway by keeping the rodent population in check.