Thursday
14th
May
A
decidedly chilly day, the temperature being more like March than May. Luckily
we managed to avoid all the heavy showers.
The
ten team members in attendance split into two groups.
Roger,
Stuart and Martin (J) first headed to the filled in bridge 41 between
Two Hedges Road and Kayte Lane. The task was to put a second coat of
paint on the safety marker railings, the ones made from old steam
loco boiler tubes.
 |
| Roger illustrating why safety marker rails are required at the filled in bridge 41. [Photo by Martin (J)] |
On
the way back to the access at Pecked Lane, then check on the infamous
‘Bonsai World’ down side crest inlet. The stream was not running
– so if it stays that way we might be able to undertake a good
internal inspection of the circular manhole next week.
 |
| Where we suspect the manhole is leaking is around the exit pipe. [Photo by Martin (J)] |
 |
The
collection of footballs removed from the line at Bishops
Cleeve. [Photo
by Martin (J)]
|
Then it was on
to Manor Lane, to fit the new head for milepost 16. Finally back to
Winchcombe to
progress the manufacture of new milepost heads; they completed that
for 15¾ and commenced on another destined for the Laverton to
Broadway section.
 |
| Mp 16 - refurbishment complete. [Photo by Martin (J)] |
Meanwhile,
the group of seven, Jonathan, Dave, Polly, Martin (S), Peter, Ian and
Andrew, made their way to the site of the now repaired slip by the
foot crossing between Gotherington and Bishops Cleeve. (See the
Gotherington Slip Repairs - Week 4 post on the Civil Engineering blog).
The tasks here were to repair the fence by the footpath on the up
(Malvern) side of the line. Dave
and Ian cleared the brambles from around the old fence. Jonathan
operated the auger this week to drill out four new post holes. Only
one stone and a few roots were encountered, so the auger behaved much
better than last week. Polly
took charge of the woodwork repair and the installation of the new
posts.
 |
| Holes drilled for the new fence posts. |
 |
Repaired
horizontal at the foot crossing - slip site in background.
|
 |
| Repaired fence - apart from one missing new post. That is on the list for next week. |
Peter
and Martin (S) used the drain rods to ensure that the bore of cross
drain 37D was clear – this tends to get obstructed with straw and
other animal bedding it does not carry a great deal of water in the
summer. Dave and Ian brush cut the ditch leading to the outlet
chamber. All four then combined to clear out the outlet chamber and
the short bore leading to it. An attempt to rod the pipe which runs
under the boundary fence meat with solid resistance after a foot or
so. Taking a photo with a phone revealed why. There is a small grill
here where the exit pipe abuts a smaller diameter field drain in
the adjoining land. We will have to ensure that this is regularly
checked for obstructions.
 |
| Peter and Martin (S) clearing the 37D outlet. The slip repair ends just to the left (low mileage). [Photo by Dave] |
 |
| Martin (S) clears the grill on the inlet to the short exit bore of 37D. [Photo by Dave] |
 |
| The surprise find, a grill inside the exit pipe of 37D. [Photo by Dave] |
As
part of the slip repair, our contractors have installed two new 150mm
perforated twin wall pipes which drain the embankment into the outlet
ditch of 37D. We are going to install a small new headwall to protect
the downstream end of these, so Andrew measured up the dimensions.
Also
measured was the exit chamber of 37D, as this now requires raising by
two block courses. The
repair has altered the profile of the up side embankment, so our plan
to install a piped toe ditch now
looks to be unnecessary,. So aided
by Martin (S) and Peter, Andrew also investigated the possibility
of installing French drains or transverse pipes instead.
After
lunch, Jonathan and Polly undertook some clearance of the ditch that
takes the outflow of cross drain 37C. This is outside of our
boundary, so the work was with permission of the landowner. This
removed quite a sizeable obstruction, we have often noted pooling
water here during the wetter months. The others turned their
attention to the low mileage down (Cotswold) side toe ditch that
leads to cross drain 37D. As this was last fully cleared a few years
ago, this was a significant task. With
the exception of a tree that will require chain sawing, they managed
to clear about three quarters of the length back to the foot
crossing.
 |
| The tree that will need removing. Peter and Dave busy clearing beyond it. |
Wildlife report:
Plenty
of bird life at Gotherington. Today we noted, robins, black birds,
gulls, chiffchaffs, great tits, long tail tits, magpies and
pheasants. Also heard, were skylarks. At lunchtime a kestrel hovered
low over our work site, seeking out any rodents. On our way back we
spotted a couple of squirrels. From a vegetation point of view, it is
going to be interesting to observe how quickly nature covers over the
slip repair site.