Full house on two scores. Firstly all
eleven members of the team were in attendance on our last working day
in January; and one of the tasks completed was reinstating the last
missing milepost. However, there are still 22 other mileposts on the
running line that require replacement with a correct GWR style head
featuring numerals in the correct font.
 |
After an absence of many years - milepost 9¼ is finally back! Toddington North cutting near the down bracket signal.
|
Thursday 30th January
With the telehandler in use to move
materials at Gretton, the team allocation to vehicles on departure
from Winchcombe Yard was 4-4-2-1. (I’m beginning to feel like a
football team manger trying out different team formations!)
Three vehicles headed for culvert 24A
at the top of the haul road opposite the Royal Oak at Gretton.
Jonathan drove the telehandler, whilst Roger, Nigel, Dave, Martin,
Polly and Peter plus most of the materials and tools followed in the
tail-lift Transit and the Isuzu. First task was to pump the outlet
pit dry. Once dry enough; the tasks were to lay some more rows of
concrete blocks for the new chamber, and to install the 450mm
diameter twinwall extension pipe and elbow. The later turned out to
be rather challenging; but the use of some recovered BR era hollow
concrete blocks as supports helped. Polly concentrated on the block
laying, Roger on the pipe installation and Nigel was chief mixer.
Dave and Martin undertaking most of fetch and carrying. Peter and
Jonathan took the tail-lift Transit to Bishops Cleeve to collect one
tonne of pea gravel from Elliots Building Supplies. They also
collected some ply wood pallets which we will deconstruct to form
shuttering. On return the pea gravel was taken up the haul road by
the telehanlder; as neither of our Transits can manage such a heavy
load up the steep slope.
 |
Chamber construction - concrete blocks up to above the top of the pies. Then it will be GRP rings above.
|
Meanwhile the other group, Andrew,
Ian, John, Stuart, headed north to Little Buckland. The route was a
little devious and scenic, as the B4632 was closed between Toddington
roundabout and Grange Farm for gas main repair. (This closure is
scheduled for a few weeks). At Little Buckland we met the owner of
Archer Farm and his drainage contractor to view the work undertaken
there; this has included a significant clean out of the embankment
toe ditch alongside the farm. During this work they have discovered a
sealed cross drain pipe running under the track. This is between
cross drains 5A and 5B, about 20 yards south of 5A. There is an inlet
pipe from the farm at the same point in the down (Cotswold) side toe
ditch. On the up side the pipe is sealed; as there is no longer a
working toe ditch at the foot of the embankment. We have quite a few
unanswered questions about this. When was it installed? It is not
shown on the original GWR plans of the line; nor on the land registry
maps. When was it sealed? We know that 5A and the down side of 5B
were rebuilt in 2016 as part of the Broadway extension work. What
structure number shall we give this? We think best not to renumber
5B, 5C and 5D. And finally, what shall we do about it? One option is
to leave it sealed, with all the northbound flow in the down side
ditch going to 5A. The other option is to unseal it and re-excavate a
toe ditch on the up (Malvern) side back to 5A. Both of these options
depend on the outlet of 5A; which outside of railway land alongside
the Little Buckland Road is a very shallow ditch which quickly
disappears. There is some evidence of overflowing from this ditch
onto the road and then back to the gullies under the bridge. Like
Laverton Meadow Lane and Didbrook No2 bridges, the road here is
susceptible to flooding during heavy rains. The road gullies empty
into some long lengths of small bore pipe with a shallow gradient. So
what ever we do, we can not add to flow in those pipes. We will make
some more investigations; then discuss with our engineers, the land
owners and the highway authority.
 |
The deepened and straightened toe ditch on the down side along side Archer Farm. Looking south from the location of cross drain 5A.
|
 |
The rediscovered cross drain and inlet pipes. Temporary board to try to get any flow to run south to 5B rather than to 5A.
|
 |
Ian, Stuart and John investigate the sealed end of the rediscovered cross drain on the up (Malvern) side. No evidence of a ditch across the field.
|
 |
Cross drain 5A outlet - beyond the fence it is a ditch that quickly disappears. Little Buckland Road at a lower level on the right - bridge 5 is just to the right of the picture.
|
A different scenic detour took the
group back to Toddington station for a walk up the line to install
the head of milepost 9¼. Unlike two weeks ago, when a trolley was
required to move the bridge rail length, we could easily manage
carrying the new head; the bolts to secure it with, a drill to drill
the holes, a spanner to tighten the nuts and, most importantly, a spirit level to ensure the head was
level. So now all the quarter miles on the running line (4¾ to 19)
have a marker of sorts – but they are not yet all the correct GWR
pattern. One marker will never have a proper post; that is 12½, as
it is inside Greet tunnel. It is a white paint mark on up side tunnel
wall. It is almost in the middle of the tunnel, 15 chains in from south (Winchcombe) portal; 17 chains in from
north (Gretton) portal. After Toddington North the group ventured to
Gotherington to repeat the head installation exercise for milepost
15½; located between the platform ends and the signal box.
 |
Proper heritage mile post 15½ sits well alongside the private collection of railway items at Gotherington. | | |
|
Whilst at
Gotherington they noted the work undertaken by our Lineside Clearance
team and a vegetation contractor on the down side embankment. This
has included the removal of a large multi-trunk tree that was growing
far too close the inlet of cross drain 35B. This clearance work has
also improved access to the chambers on the boundary hedge/fence for
the pipe which connects the cess drain in the old 6 foot through the
platforms to cross drain 35A. So a quick check that all was well
there was undertaken. Then back to Gretton to join up with the rest
of the team opposite the Royal Oak.
 |
What
a transformation - the down side embankment at Gotherington with the
stump of the tree removed from the inlet of cross drain 35B.
|
Before a late lunch, all 11 of us
spent a hectic hour finishing today’s chamber block laying and
packing pea gravel around the twinwall extension pipe. When using
rapid curing cement you have to be quick!
 |
Orange army! Seven of the team (and the shadow of the photographer) at work on 24A.
|
 |
Stuart ensures pea gravel is packed under the extension pipe.
|
After lunch Jonathan with the
telehandler and Ian and Stuart returned to Winchcombe Yard. Here the
task was to extract some old dumpy bags filled with pea gravel and
other material which we can use as infill at 24A. These were at the
back of an area which S&T require for outdoor storage. As some of
the old dumpy bags were rotten, this task involved quite a lot of
shovelling to transfer the contents to better condition bags. The
rest of the team tidied up the site at Gretton. Another example of
inter-department cooperation here; PWay have loaned us a lockable
tool store to deploy on site. This means a lot less shifting of tools
and items like bags of cement at the beginning and end of each days
work.
 |
Just enough warmth in the sun for an al-fresco lunch. Use of the ballast shoulder as a seat can only be undertaken when the line is closed under a possession. (Left to Right Nigel, Roger, Martin, Dave - the other team members preferred the tail lift of the Transit and the back of the Ranger).
|
 |
Sate of construction at the end of the day. Another 20 blocks needed for the chamber and around 3 more tonnes of pea gravel to cover the pipe. Then it will be bring in the infill.
|
 |
The tools that won't fit the tool store are loaded on the tail lift Transit for the journey back to Winchcombe. Its our favourite view from the line here - at its best on a clear sunny winter's day with no leaves on the trees.
|
 |
Last task was to turn off the pump on the inlet (down or Cotswold side), so water starts running through the new extension for the first time.
|
Next week we plan to complete the
block courses of the new chamber; then we can start the task of
infilling the hole. So our ‘shutdown’ project is on schedule, we
are looking forward to seeing Cheltenham Gold Cup race trains heading
past a graded landscaped area at the top of the haul road.
Wildlife report: Close
encounters with large mammals today – a large dog fox at Little
Buckland and a couple of muntjac deer at Gotherington. Bird wise
nothing unusual to note – just the plentiful number of red kites,
kestrels, buzzards, and robins. Very noticeable was an increase in
back birds, both in numbers and the volume of their song. It must be
that spring is on the way! Confirmation of this was the observation
of the first flowering of snowdrops . On the sunny side of the cutting
at Toddington North it is very apparent the other spring bulbs are
rapidly growing. Not quite so on the shady side.
Regarding the 'new' cross drain at Archers Farm, there is the possibility that over recent years the field on the Malvern side has been worked to provide a much larger and flatter field than was there originally. I can't imagine that the field was this large pre 70/80's. Possibly ridge and furrow with the culvert running through a 'furrow/stream' outflowing into the stream at the far boundary. If the landowner can be contacted, ask of it's history.
ReplyDeleteAndy. We have come to the same conclusion; the newly discovered pipe runs straight from that in the farm, so is very likely to be following a long gone furrow. We have decided to leave this pipe sealed; so anything from the farm's barn will go into the deepened ditch on the down side; then to 5A. We have a meeting with GCC highways next month; the subject of the Little Buckland Road ditches will be on the agenda.
DeleteAndrew.