Tuesday, 30 July 2019

The down side on Monday

Monday 29 July 

It's been perfect weather for bricklaying for a change, even better, it's been ideal for getting some concrete down so that even more bricklaying can be done. The spotlight is slowly moving over to the down side with the channel wall already raised, the main thrust is around the inlet and cess outfall that need to be constructed. 

The footings for the south wall extension have been dug out, they are following the line of the brick channel that was covered by pipe when we started here. This has saved a bit of effort as there's a solid base to work up from. 

Nigel digging out the footings on the down side
(Photo: Alastair) 
Down side south wall, increased height  
Footings for the wall extension 

More supplies were brought down from the yard to keep the team busy. 

Bricks and cement loaded for transfer 
Dave stores the bricks under the bridge
(Photo: Alastair) 

The bit of grass remaining between Culverts 11A and 11B on the up side was cut back. 

Area needing a trim 
Stuart runs the flail along the hedge line
(Photo: Alastair) 
Clear run between the culverts 

The shuttering was removed from the up side cess outfall 

Up side cess outfall 
Roger adding the new headers to the south wall 
Roger, Stuart, Nigel and Dave all busy on the down side
(Photo: Alastair) 

There's some old concrete left where the new wall is going to go, we are just building up on top of it. 

Shuttering down for the concrete 
Part of the concrete footings laid 
Culvert 11A, Down side, South wall level raised 

By the end of the day, the progress was visible 

Down side, original south wall raised 
Up side, 125 headers laid out ready to go on the north wall 
Brick arch, the former will be ready for moving on Thursday 



9 comments:

  1. What a Gang, real pro's at work. I passed by today (30th) on the cushions in the pouring rain, and noticed all the materials tidily under wraps, is all this rain running where it should do now? It must be pleasing to see the water draining away as should even if the down side is not quite complete yet.
    Powli Wilson

    ReplyDelete
  2. The work done is absolutely tremendous and each and everyone involved deserves praise. Just a question though is the crack on the wing wall safe as well as the coping stones on the top. Is that going to be repaired as well or is it still structurally sound.
    Stephen Smirmth.
    Secunda
    South Africa

    ReplyDelete
    Replies
    1. I'd asked about the crack (it's in the comments a month or two back), and the reply indicated that apparently it is stable (it's been just like that for donkey's years, and old grouting in it has remained intact), but they are keeping an eye on it.

      Noel

      Delete
    2. Found it; it's in the post from 11 July 2019, 'Stanton - Moving up a gear'; there's a para in the post itself about it.

      Very interesting to look back at the early posts, to see the images of how things were to start with. Tremendous progress/improvement since then! Great job, all, and a lot of hard work!

      Noel

      Delete
  3. What a hell of a job. Very well done gentlemen. You will be pleased to see it finished

    ReplyDelete
  4. Thank you all for the kind words; As we are all volunteers, we are doing the job because we want to not because we have to. Perhaps the enthusiasm for what we are doing shows through in the end product.
    Stuart

    ReplyDelete
  5. Sure does! (as they say across the "Pond".

    Powli Wilson

    ReplyDelete
  6. Another great job almost completed, do you keep technical records of the work done? Well done to you all a very profesional job done there, now i have a small job for the team i will call it HS2A for now, when could you start? LOL!!!!
    Regards
    Paul & Marion.

    ReplyDelete