Monday 15 July
Concreting day, even with 4 of us in it was hectic so the pictures are a bit sporadic. The concrete arrived this morning and we took 6 CuMtr of 30N mix. having the digger to handle it meant that we could work with it fairly dry adding water as it was tamped into place. It was non-stop until 12:00 so we did some easy jobs in the afternoon.
Both Nigel and Dave managed to get some brick cleaning in before the concrete arrived and again after it was all sorted.
|
Dave brick cleaning on the up side |
|
Nigel on the down side |
|
Steve at work when we arrived |
The end of the up side cess ditch is going to get a wing wall to sort out the erosion in that corner. First job as always is to get some footing in and having the mix on hand was an opportunity too good to miss.
|
The old temporary bridge gets a new life as shuttering |
The down side cess extension is going in today, having no trains on this section of track allows the spoil to be recycled into the ditch as backfill
|
First bucket of 6F2 going in as a sub base (Photo: Alastair) |
|
Filling the scour at the end of the original cess drain |
Then is wall all hands to the pumps to deal with the EasyMix delivery
|
Mix dropped from the bridge |
|
This is definitely faster than our mixer |
|
It just keeps shooting out |
The gabion base on the down side was first to get supplied
|
Richard and Steve laying the gabion base |
Then attention moved to the up side
|
The up side gully pipe backfill |
|
Steve, Nigel, Stuart and Dave (Photo: Alastair) |
|
It wasn't all moved by digger, and this picture wasn't posed by actors 😅 (Photo: Alastair) |
|
Richard came round to lend a hand |
The vibrating poker was used to get all the air out, the picture below shows how the level drops as concrete compacts...
|
Dave on water, Alastair with the poker and Nigel keeping the wires out of the way |
After compacting, a second layer was added to shape the edge up the side wall and fill some hollow spots in the track
|
Moving the second layer into place (Photo: Alastair) |
This is where we all got a go at the concrete stomp, it's a bit like line dancing without the music 🤣
|
Nigel fills a hollow while Dave concrete stomps |
|
This took a lot of stomping |
|
Down side gabion base finished |
|
Up side cess outfall footings done |
While we were all up to our necks in concrete, a delivery arrived ready for the next stage - 100 mm Concrete Blocks for the down side wall along the hedge line, plus 2 tonnes of concreting ballast.
|
Ready for Roger coming back from his holiday 🤭 |
There was just enough mix left to concrete the down side cess extension pipe into the old SGW cess drain pipe.
|
Long reach bucket to pick up the concrete |
|
Twinwall and SGW concreted together |
|
Down side cess backfill started |
The dregs that were left were used for a sub base for the scour protection at the end of the culvert channel
|
Stuart doing the concrete stomp while leaning on a shovel (Photo: Alastair) |
|
Up side scour protection sub-base |
The concrete may not have fully cured, but it was tested as Steve collected more spoil for the down side cess. There was no sign of movement with 7.5 tonnes of JCB sitting close by.
|
Load testing |
The heap of spoil removed for the hard-standing has gone, it's now on top of the down side cess, the site is getting a bit tidier.
|
Hardly and spoil left to spoil our views |
The old concrete covering the brick arch got nibbled away this afternoon, it needs to be cut back a bit to get the broken bricks out so that the arch can be reconstructed .
|
Brick arch covering nibbled away |
A very tired gang headed home happy that the view from the bridge has significantly improved today. It feels like we are over the hump now on this project.
|
Up side view from above |
What can you say? Words fail, Brill' What an amazing days work and so carefully planned. Wondeful, congrats.
ReplyDeletePowli
Fantastic lads, great bit of work and really appreciate the blog updates
ReplyDelete