Thursday 19th March
A last minute change of plan for us today, as C&W required the tail-lift fitted LWB Transit to
collect a piece of machinery from Cheltenham. We also required it to
deliver concrete catch pit rings to Stanton Yard. So our plans
changed – no work on the steps above the River Isbourne to enable
deployment of extra manpower at Stanton to enable offloading of the
rings and returning the LWB Transit to Winchcombe for C&W use.
So Jonathan loaded the five concrete
rings on the LWB Transit with the telehandler. Then he departed to
Stanton with John driving the Transit. Also heading that way in two
other vehicles were Martin (S), Martin (J), Peter, Dave and Nigel.
[One downside of a larger team size is that we need several vehicles
to get us all to site. The work at Stanton was to replace some broken
rings on the cess chamber immediately on the high mileage up side of
Stanton Bridge. As you can see from the photographs, this is very
close to where fresh supplies of ballast are delivered and then
collected. Hence this chamber is prone to damage from close
encounters from vehicles. First task was to remove some of the
ballast hep from around the chamber and then the two damaged rings.
We inserted four new rings, thus making the chamber higher and more
visible. The telehandler made this job as lot easier and safer –
these concrete rings are very heavy. Moving them by hand needs four
strong folk. We covered the chamber with a blue mesh lid, bolted
down, and placed two blue painted marker posts in front of it. There
is now no excuse for failing to spot that chamber now.
 |
| Martin (S) and Martin (J) removing some of the ballast pile around the chamber. [Photo by Dave] |
 |
| Unloading the pallet of rings to enable the Transit to return to Winchcombe for use by C&W. [Photo by Dave] |
 |
| Jonathan carefully reverses down the slope to the trackside with the first replacement ring. [Photo by Dave] |
 |
| Martin (J) directing the placement of the third ring.[Photo by Dave] |
 |
| The completed stack of rings with lid and markers. [Photo by Dave] |
After the work at Stanton, Jonathan
returned the telehandler to Winchcombe. His next task was to sort out
a flat tyre on the Isuzu pickup. The next jobs for Martin (S), Martin
(J), Peter, Dave and Nigel were further north. These were to install
lengths of bridge rail for the posts of replacement mileposts 6 and
6¾. The bridge rail lengths for mileposts are 6 foot long; so these
are quite heavy too. They require a two foot deep hole in the ground
– another task requiring some muscle power.
 |
| Martin (S) and Peter inserting the new post for milepost 6¾. [Photo by Dave] |
Final task for the group of five was
to complete the checking of the distances between the mileposts up to
Broadway. Martin (J) has repair our measuring wheel using plastic
welding; whilst Martin (S) demonstrated some skilful balancing by
running the wheel along a rail head to avoid irregularities caused by
uneven ground.
Meanwhile back at Winchcombe Yard,
John had joined Ian and Andrew working on two GRP catch pit rings
that are destined for the new chamber on the crest at Stowe Road,
Toddington. The task was to cut a 265mm diameter hole in the ends to
take the inlet pipe of the new crest drain. Whilst these GRP rings
are considerably lighter than the concrete rings, they are extremely
hard. Hence the hole cutting took quite some time, using a variety of
power and hand tools.
 |
| Ian preparing to cut the GRP rings. Fist drill a small hole in the middle of the cut out to enable marking a circle leaving equal amounts in each ring. |
 |
| Completed set of rings and length of pipe test fitted. Excavating the ditch and fitting this at Toddington is next week's task. |
After lunch, Jonathan and John make a
quick visit to Pecked Lane at Bishops Cleeve. The job here was to
install some additional warning signs by the footpath gates.
Unfortunately, the fixings on the back of the signs proved
incompatible with the tubular posts already in place. So a return
visit will be needed with some different sized fixings.
Wildlife
report:
Spring
had certainly
sprung
- this
was the warmest and sunniest workday for us so far this year.
Consequently we observed a noticeable increase in inset activity,
spotting solitary
and bumble bees and several species of butterfly. At Winchcombe we
observed at leat six magpies which appear to be nesting towards the
school. They were being mobbed by at leat three crows. The yard’s
resident robins were also noted. The change to spring weather has
certainly brought out the blossom on the blackthorn trees and bushes,
and on a couple of cherry trees. Daffodils and narcissi are now just
past their flowering peak, whilst in a sheltered spot near broadway
we spotted primroses in full flower.
 |
| Primroses. [Photo by Dave] |
No comments:
Post a Comment