After our very wet, but short day,
last week we did not have high expectations for this week. However,
the weather was slightly better than forecast, just damp rather than
wet, not too cold and even a few patches of blue sky and some brief
sunny periods. Plus, we noted the first signs of spring.
Thursday 22nd January
Eleven of the team reported for work
today. The large number enabled a split into two teams heading for
two completely separate work sites.
Jonathan, Dave, Roger, John and Martin
headed south to Bishops Cleeve. The first task quickly undertaken was
to check for any build-up of silt at the down side entry of culvert
39A. This is the one close to Pecked Lane foot crossing. It was
flowing well, so no work was necessary here. When the flow eases off,
we sometimes get a build up of silt in the entrance.
Next task for the team was to use the
heavy duty brushcutters to shred the remaining cut vegetation on the
up (Malvern) side cutting. There were three spots, one just before
Two Hedges Road and two after. We are looking forward to seeing
grass, rather than bramble or scrub, growing on this cutting.
 |
| Up side cutting south of Two Hedges Road looking towards Cheltenham. Much neater with the removal of cut vegetation. [Photo by Dave] |
Further along, where the cutting
transitions into an embankment, the group removed some damaged and
redundant post and wire fencing. This is where the houses on Paget
Road back onto the line, they now have their own fences. The wire
became scrap; but some of the posts were recovered back to Winchcombe
Yard as we can reuse them elsewhere.
The big task for the team was to full
clear the silt from the down (Cotswold) side inlet of syphon cross
drain 40A. This was an interesting task. After moving aside one of
the concrete sleepers which covers the inlet channel, they removed
some rather smelly silt. This revealed quite a good flow coming from
under the adjacent farm track and footpath. In the base of the
chamber is a circular hole full of silt and debris. The water flows
over this, then into a pipe which heads down cutting side. As we have
never found the outlet of the syphon, the exact arrangement here is a
bit of a mystery. Now with the silt cleared from the inlet, we will
return to undertake a further flow test with dye. That will have to
wait for a few week though, as the vacant up side track bed is not
accessible until the completion of the laying of a replacement S&T
cable from Gotherington to Cheltenham.
 |
| 40A inlet with one covering sleeper removed. [Photo by Dave] |
 |
| 40A pipe coming from under the farm track & footpath. [Photo by Dave] |
 |
| 40A exit to the syphon. [Photo by Dave] |
The other group, Dee, Andrew, Ian,
Nigel, Peter and Stuart, headed north to Toddington. Their task was
to commence the construction work to alleviate the field and road run
off which has afflicted the down side low mileage of Stowe Road
Bridge (13) for many years. The first task was to complete the
excavation between the bridge and the existing cess chamber. Then
Nigel and Peter mixed three barrow loads of concrete; for careful
insertion. Stuart and Andrew inserted steel reinforcing bars, and
then carefully levelled out the concrete. This will form the base for
a small retaining wall to keep silt away from the cess; and for the
extra course of bricks to raise the chamber.
 |
| Stuart tamping and levelling the concrete for the wall base. |
 |
| Close up showing some shuttering to avoid cementing in the S&T point cable which runs below the cable trough. |
 |
| Peter and Stuart start clearing up after finishing the concrete laying. Having no rakes of stabled carriages in the platforms at Toddington makes working here a lot easier. |
Meanwhile, Dee and Ian surveyed the
cutting side. We suspected there was an existing land drain – this
was easy to find today as it was running well. Unfortunately it
emerges some way up the cutting side; water then running down the
cutting side into the cess almost underneath the S&T cabinet. Not an ideal situation. This field drain probably extends beyond
the railway boundary. The probable line of this drain was marked with
blue marker paint. We then decided to modify our plan for the
improvements here. We marked out the line of a new crest drain from
the boundary corner by the road to site of a new chamber above the
existing field drain. This will save the effort of constructing a new French drain or pipe run down the side of the cutting. We measured up
and test fitted a length of flexible pipe to extend the field drain
to the cess chamber. The diameter of the flexible pipe was perfect –
but it was not long enough. So something for the shopping list this
week.
 |
| Ian removes a tree stump just below where the field drain exits. |
 |
The crest of the cutting - just visible marking for the suspected run of the field drain and the location of the new chamber (to left of help of vegetation). |
 |
| Test fitting of flexible pipe to extend the field drain to the cess chamber. |
After lunch, Stuart and Ian undertook
some flow tests with the marker dye. This showed that both the up and
down side cess drains flow north from Stowe Road towards Stanway
viaduct. The connection under the tracks to the cess drain in the six
foot between the platforms at Toddington was not flowing. The other
four used the laser level to take readings of the levels of the land
on the crest of the cutting. The important item to determine from
that data is the depth of the new junction chamber; and consequently
the number of chamber rings we will need.
 |
| Ian and Stuart returning from the dye testing. Note the sunshine! |
 |
| End of day - ply covering the curing concrete and blue mesh lids to cover the holes. |
Wildlife report: We spotted
some welcome signs of spring approaching. By the fence line alongside
Stowe Road bridge was a patch of snowdrops. At Bishops Cleeve, the
group there noted increased activity by long tailed tits – the down
side cutting by Two Hedges Road has some ideal nest sites. Whilst at
Toddington, two robins serenaded us whilst taking lunch on the
platform. They certainly were having a singing competition; maybe two
males at the edges of their territories, or a maybe a courting
couple. Not quite wildlife, but the team members driving home towards
Broadway reported a spectacular rainbow, a full 180 degrees arc
across the sky.
 |
| Sign of spring 1 - snowdrops at Toddington. [Photo by Dee] |
 |
| Sign of spring 2 - bulbs at Bishops Cleeve. [Photo by Dave] |
No comments:
Post a Comment