Monday 24 February
It was a wet start this morning so we took shelter in Carriage & Wagon to cut some wood to make new moulds for making 1800 mm chamber lids. The 900 and 1200 mm we made last year have been so successful we're venturing into bigger things. Next off was a trip to Bridge 37 slip at Gotherington to see if the drillers has got any soil nails in. Then it was back to Gretton for more fun at Royal Oak.
|
Dave and Martin cutting the sides for the second mould |
The drilling rig is working at Gretton, there's over 300 nails to go in to stabilise the slip and the embankment at each side of it.
|
Soil nail insertion |
|
Crack half way down the slope |
|
Rabbits burrowed under the old concrete fillet, must be using it as a big lintel 😊 |
|
The ever growing snout at the toe |
|
Driller at work |
Round at Royal Oak there was more cess drain to clear, one patch had 400mm of building sand on top of the blocks, who knows where that came from; possibly the build of Gretton Halt years ago.
|
The Gretton sand pile |
|
Dave and Martin taking levels along the down side cess drain |
|
The level had to be moved every few chambers round the bend |
Note: no trains running today so the is level standing in the track.
|
More run off at the trouble spot |
|
Collection into the pipe not going too well |
It's staggering the amount of spoil removed from the top of the drain, this is just to get to the blocks which should have been left exposed
|
The spoil heap from a 12m stretch of drain |
|
Progress along the cess today |
Tuesday 25 February
There was a meeting at Gotherington with the contractors and the design team. It's looking promising for having the slip stabilised ready for reopening on 7 March. It was decided that the soil nails through the slip should be extended to 18m.
|
Drillers hard at work installing soil nails |
|
The end of the nail waiting for the plate |
|
3m lengths laid out ready for installation |
|
Drilling rig on the bench under the face |
|
Middle row of nails |
|
Discussions in full swing |
Stop off on the way past to check how much spoil and aggregate is left at Stanton Yard, not much!
|
Stanton Yard stockpiles |
Thursday 27 February
A bit of a shock to the system this morning, British weather can be changeable. Lego blocks in at Winchcombe cutting down side to retain the toe of the slip and the the 5m steel sheet piles arrived for rail transport down to Bridge 37. Then we had a Health & Safety inspection at Royal Oak, it's good to get a specialist view on what we have planned, it reinforces good practice.
|
Cotswold morning, almost Spring 😊 |
|
Winchcombe retaining wall in place |
|
12 tonnes of 5m steel sheet piles |
Added excitement at Royal Oak, the tamping machine passed through this morning on it's way further down the line. Strange to see rail traffic, there hasn't been any since we started here.
|
Tamping machine running through |
First job today was moving the excavated drain blocks nearer the line so they can be loaded onto a trolley to take them to where they can be loaded for transporting off site.
|
Blocks piled ready to go |
|
Too much water in the trouble spot still |
|
A couple of grips pulled into the slope |
More water ponding above the toe on the up side slope, another job on the list
|
Wet area on the up side slope |
|
Michael and Dieh digging the grip in the crest |
|
Andrew and Martin taking the cess levels on the up side |
|
It's very wet on the down side crest |
|
Water flowing over the crest drain |
The down side crest pipe should be intercepting most of the run-off water, it's in a worse overgrown state than the cess drain. It's going to be awkward to get a machine in to excavate it until the ground dries out.
|
The water goes into the pipe eventually, just not where we need it to |
Down at Gotherington it's a summer day almost, the howling wind is a tad fresh though.
|
Nails laid out ready to go in, the face has crept back to under 3m here |
|
Face at 3.4 m in places now, it doesn't help having a 10 tonne rig on it |
News in that the piling machine weighs in at 35 tonnes, getting it in may be interesting
|
Snout cracking at the toe |
It was a different day on the way back, hopefully the snow flurry this morning will be out last for the year.
|
Cotswolds in the setting sun |
Saturday 19 February
Leap year, so we get an extra day for working 😉
It's been raining for the last 24 hours, this calls for a quick check on the bridges that normally flood. Bridge 6 Laverton and Bridge 16 at Didbrook are both in dips and catch quite a bit of surface water, both were clear today. While Michael and Dave went north, Stuart and Roger went to have a quick check on the slip at Gotherington.
|
Bridge 6 Laverton, gully drains working (Photo: Dave) |
|
Culvert 16A down side overflow (Photo: Dave) |
|
Bridge 16, Didbrook No 2, clear |
|
No drilling today, rig parked off the slip |
|
Bridge 37 slip, soil nails in the face |
|
Bridge 37 up side slip at track level |
|
Bridge 37 up side slip, slope toe |
|
Bridge 37 up side slip Cracks in the snout at the toe |
|
5 m steel piling stacked up at Gotherington |
On the way back we spotted that Culvert 31A at Prescott Road has backed up from the outlet. The main issue here is that there is only a 6" pipe between the outlet channel and an overgrown ditch along the roadside.
|
Culvert 31A, up side outlet backing up |
|
Culvert 31A up side headwall submerged |
Round at Working Lane, Michael was preparing the patio area outside the welfare cabin, then we did a bit of road repair on the lane. Even the Transit was scraping the ridge in the middle of the lane, so we needed to sort it out.
|
Michael with the whacker plate |
|
Dave clearing the end of Culvert 24C again |
|
Culvert 24C up side running again |
|
Michael and Dave spreading the hardcore on the lane |
|
Working Lane one side built up |
Roger was back today after a short break, his first job was to inspect the low mileage wing wall on the down side of Bridge 25. The embankment around the end of the wing wall looks to have receded, the red bricks would normally be underground.
|
Roger working out how to repair the wing wall |
The flow on the up side of Culvert 25A is mainly flowing along the ditch at the toe from the outlet of Culvert 25B.
|
Culvert 25B outlet ditch |
Up at Royal Oak, Michael and Dave started to cut back the hedge, we need to get into the crest drain as it has overgrown and the run-off from the field is cascading straight over it.
|
Royal Oak, Roger off to look at the down side cess |
|
Royal Oak down side, run off from the field into the cess |
|
Michael with the brushcutter on the crest |
|
Down side cess, drain blocks inhibiting the flow |
|
Royal Oak, up side pond |
|
Royal Oak, Dave cutting back the hedge |
|
Royal Oak, another hail shower passing through |
|
Royal Oak up side turning area extended |
Looks like an awful lot of work still to do to get the water away from the railway. However, the work that you all are doing will be well worth the effort in the end.
ReplyDeleteRegards, Paul.
I think the site of the half built halt at the Royal Oak was on the Malvern side.
ReplyDeleteJo, You are correct, the remains of the platform footings are on the up side, but it's the only explanation I cold come up with for building sand on the down side. Perhaps it was a stockpile for the work. There's no other work in that area which would require what looks like a ton of sand
DeleteHi. I'm just curious. Are the blocks in Winchcombe cutting permanent or temporary.?
ReplyDeleteTemporary, according to the press release on the GWSR site.
DeleteNoel
Thank you.
DeleteThe current plan is to remove them in October to effect a full repair, it depends on the insurance companies as they are funding the works
DeletePleased its an insurance job !
ReplyDeleteIt is an excellent blog, I have ever seen. I found all the material on this blog utmost unique and well written. And, I have decided to visit it again and again. Plantejord.dk
ReplyDelete