Sunday 2 February 2020

Back to the future, the builders return

Thursday 30 January

Today was spent inspecting things and working out what we need for the next project. Some work on Winchcombe cutting slip is due to start next week, this will stabilise the slip so that the full remedial package can be put in place in due course. First off we ran up to Stanway Viaduct, the southern end has been competed and track laying will start at the weekend. On the north end, pit 14 the last of the batch was being excavated and the rest were being backfilled or being prepared for backfilling.

Stanway Viaduct drainage pit refurbishment
Stanway Viaduct drainage pit 13 stone backfill in 
Stanway Viaduct drainage pit 12 ready for backfilling 

The River Isbourne has turned green, this is the dye we dropped in the down side crest drain chamber up on Winchcombe cutting to prove the flow reaches the river where we expected. The dye is bio-degradable and will fade away as it flows downstream. Andrew and Michael waited for 40 minutes watching the stream for the dye and then gave up. An hour and half later there was a call from the contractors at the river to say it had turned green. Where the water had been for all that time is a bit of mystery still.

Tracer dye reaches the Isbourne 
New safety handrails being erected on the down side headwall 
Down side steam outlet at the river 

In between jobs, Andrew and Michael refitted the jockey wheel to the flail.

Many hands make the wheel work in this case 

After lunch we headed out to Working Lane at Gretton on a reconnaissance trip to work out if it was feasible to resume operations on Culvert 24A.

Very wet ground around up side of Culvert 24C 
Land next to the haul road up the tunnel is still wet 

The cess outfall has been spotted on Culvert 24A up side 
Gretton Meadow aka Royal Oak 

There was a headwall on the end of the crest drain where it joins Culvert 24A, it butted up to the headwall on the culvert. The redesign is in the form of a quadrilateral that will be covered when it's up the ground level. 

Culvert 24A crest drain chamber as left in October 2019 

Some additional drainage work needs to be done around the Gretton meadow area on both sides of the line. 

Down side opposite Gretton Meadow 
Base of the slip repair needs to be drained 
Michael skirts a boggy patch on Gretton meadow 

On the way we looked at Culvert 24C down side outlet, improvement works are planned here that will add a headwall and silt trap. It's prone to blockages as the grille gets covered in debris. 

Culvert 24C down side outlet before clearing  
As Michael has some wellies, he gets the wet jobs 
Culvert 24C after clearing the grille 


Saturday 1 February

As the sun was shining and the wind was blowing we decided on two streams of work today. Dave and Michael shot off to Gretton and Culvert 24A to resurrect the rebuild of the down side crest drain chamber that was started back in October, it was then abandoned when it got too wet and other interests intervened. Meanwhile the other operative went to Winchcombe Cutting to continue with the ditching work along the down side crest.

Truck loaded with bricks and barriers ready for the off 
Stacking the unloaded bricks in the shadow of monster truck 😃
(Photo: Dave)
Micheal back on the bricks
(Photo: Dave) 
A course of imperial solids goes on first to level up
(Photo: Dave) 
Someone has to stick their head above the parapet
(Photo: Dave) 
Mixer loaded ready for a quick get away
(Photo: Dave) 

Back at Winchcombe cutting the down side ditch got extended a bit further along. Work on this will be put on hold next week until the contractors build a haul road up the slope to remove the failed soil from up side slip. 

Making the most of the weather 
Ditch work in progress 

When the bucket hits an buried obstacle it's always best to proceed with caution until you identify what it is. In this case it's a chamber we didn't know existed.  

Bricks and bridge rail uncovered in the ditch line 
Top of chamber scraped clean 
24" crest pipe running in 
24" crest pipe running out, mystery pipe running in from the field 
Concrete fencepost dug our of the ditch 
Winchcombe Cutting down side crest, ditch extending 




12 comments:

  1. Amazing. Do you think the field pipe in the newly "discovered" chamber has been damaged/blocked in the field?

    Powli

    ReplyDelete
  2. Thanks for doing the blog lads, always find it interesting

    ReplyDelete
  3. Are there any circa 1900 GWR drainage drawings to help you guys hidden away at York?

    ReplyDelete
    Replies
    1. We have the 1902 design drawings but not the as built, plus there have been changes since. There could be some at the GWR Museum in Swindon but haven't chased them up as yet

      Delete
    2. As I live in Swindon and know people down there do you want me to check it out for you

      Regards

      Richard Symonds

      Delete
    3. Hi Richard, That would be helpful if you get the chance. There may not be much, it would only be the major works that got documented. The drainage at Winchcombe was replaced in that late 1940's, the track was lifted and a fresh gravel sub-base was added. That may be in the collection

      Delete
  4. Hi GWSR DG - went to STEAM today to ask the question and was fortunate enough to meet the lady responsible on her way off for the weekend. Her name is Elaine Arthurs and she told me what they hold in the archives is now computerized and searchable and invited me to contact her with my specific requirements. As I am sure you would not want me to act as a Post Office may I suggest you contact her direct with your requirements referring to my conversation with her. Elaine's email address is earthurs at swindon.gov.uk.

    Let me know if you want me to collect anything to bring over meanwhile keep up your outstanding work.

    Regards

    Richard

    ReplyDelete
  5. 2 points , i met Elaine Arthurs at STEAM Swindon 15 years ago on business when doing Travel Guides and have also persuaded Great Railtours to do a GWR round Trip holiday with Didcot , Swindon and the GWSR which is now up and running , they visit twice during our season .

    second , we have lots of Scrap sleepers from 60 replacements by Pway this past 4 weeks , may I suggest that we and you utilize them to stabilize and improving the access road from Working lane to Culverts 24-26 ,so motor traction can improve along the lower part of the route which is in terrible condition , john M.

    ReplyDelete
    Replies
    1. Hi John, we are working on Culvert 24A at the moment, I have seen your piles of sleepers, I was expecting someone to come and take them away :-). Part of the project is put some new drainage in the toe of the embankment which may improve things on the haul road up to Gretton Meadow. The drain gang seem to get pulled in to fix random trackside issues, no doubt highway maintenance will be great to add to our CV's :-) Stu

      Delete
  6. Pleased that you have met Elaine Arthurs John, a nice lady who has undertaken to look at her records to see what information is available to the Drainage Gang. All they have to do is to establish contact which I am sure they will do!

    ReplyDelete
    Replies
    1. Hi Richard, thanks for the update, I will contact Elaine at Steam and see if there's anything relevant. Stuart

      Delete
  7. Hi Stuart,

    Please let me know if there is anything more I can do to help.

    Regards

    Richard

    ReplyDelete