Saturday 10 August
It's supposed to be the middle of summer and what do we get today, gale force wind blowing across the top of the embankment with scattered heavy showers. Luckily it was fairly sheltered down under the bridge so we cracked on.
Slight change in the plan today, it was too wet to concrete the down side cess base, that left us with the only dryish option; the up side end of the brick arch, this got coated in the red 30N mix. It should look very attractive when it's dry.
|
Stanton is Summer - it sums up the weather today |
Alastair was missing today, Nigel got to be in charge of the mixer and a good job he did too, especially with the unfamiliar Forest Red chippings.
|
Nigel at the mixer |
Dave's first task was to build some shuttering for concreting over the brick arch. This brought out another talent he has kept under wraps.
|
Dave digging out for the shuttering |
Meanwhile, on the down side Michael had installed a bypass pipe for the cess, this took the flow away but it was still too boggy for concrete.
|
Down side cess temporary bypass pipe |
The new south wall on the down side is taking shape, Roger was building while Michael backfilled the void behind the wall with concrete and stone.
|
Michael adding stone to fill the void behind the south wall |
|
Roger building up his muscles with the blocks |
|
Blockwork finished |
By this time, Dave's shuttering was ready
|
Arch shuttering |
|
Dave adds some support to stop it moving |
|
Painting a coat of PVA to seal the new mortar joints |
|
Brick arch ready for the Forest Red 30N concrete |
Michael took on the task of plastering the concrete skin on the arch
|
Repairing the crack |
|
Looks as good as new now |
A test mix of concrete was dropped into the end of the up side cess to finish off the junction point.
|
Up side cess outfall shuttering |
|
Michael showing that if the mix is right it will hold in place |
There's nothing like working with an audience...
|
Possibly another design conference |
Using blocks for the backing on the down side south wall extension has cut down the build time considerably.
|
Roger waist deep in the channel |
|
Brick skin almost done |
All that work building the brick arch, only for it to be covered from sight.
|
Michael may take up plastering next |
With the south wall gone as far is it can, a start was made on the north wall
|
Roger puts a slight curve on the north side |
By close of play, a fair bit had been achieved despite the weather.
|
Roger tidies up the pointing |
|
Down side end of day |
|
Up side end of day |
Looking thought the bridge, there's still water pooing in the centre, we are thinking about installing another gully drain in the middle of the roadway. The surface can't be levelled any higher as it would decrease the clearance required for the traffic.
|
Looking though the bridge up to down side |
Let's hope that no tractors need to use the bridge until the shuttering comes down on Monday.
Well done lads, thanks for the blogs
ReplyDelete