Thursday 15 August
The gang split up this morning with Stuart going to meet the forestry contractors to discuss clearing the fallen trees at Culvert 45A in Cheltenham. The rest headed off to Stanton and Culvert 11A for more bricklaying and concreting. The weather has been variable this week, but we managed a dry day which let us get a lot done.
Starting with Culvert 45A at the extreme south of the trackbed, we need to clear it for a structural examination by consulting engineers, they will pronounce on the stability of the brick arch structure. As it has been left since BR days it has become somewhat overgrown. The area looks like it has been used as an adventure playground by the local children with some fallen willow trees to use as bridges over Wyman's Brook.
|
Culvert 45A up side, covert location |
|
Culvert 45A up side, close up |
|
Culvert 45A up side, the obstacle course |
|
Culvert 45A up side, a bit of headwall visible |
|
To the south of Culvert 45A there's what looks like a storm water drain outlet |
|
Culvert 45A up side, trees that need to go |
|
Culvert 45A up side, another tree bridging the stream down stream |
Back at Stanton Michael had started by completing the headers on the south wall extension.
|
Michael using the long level (Photo: Alastair) |
|
South wall headers almost done |
Next on the list was completing the concrete pour for the down side cess outfall. About ¾ of a tonne of concreting ballast went in on Monday, that had gone off so the top layer could go on.
|
Down side cess rough concrete base layer |
The bypass pipe needed to be removed first and the pump set up to take the water over the concrete.
|
Hoy! mind my new bricks with that hose (Photo: Alastair) |
|
Pump in and working |
|
Michael make strides with the north wall brickwork |
|
Concrete coming in via the top of the gabions a barrow at a time |
The concrete is for the footings of the new walls to protect the gabions and to hold the hedge back, it has a depression in the centre to direct the normal flow
|
Stuart trying to make a good impression (Photo: Alastair) |
|
North wall up to header level (Photo: Alastair) |
|
Pointing up the headers on the south wall (Photo: Alastair) |
Up at the concrete plant Dave was multi-tasking, barrowing the mixes down to the outfall and giving Alastair a hand with the mixing.
|
Alastair keeping a watch on 'Dave the mixer' |
|
Action shot of how not to spill ballast (Photo: Alastair) |
|
Down side cess outfall top part finished |
More concrete was required to reinforce the new south wall, it acts a barrier between the wall and the roadway
|
South Wall - longitudinal strengthening with rebar |
As there was still some ballast left, the small triangle at the foot of the outfall got a base layer, this will stop the soft clay bubbling up through the top layer
|
The missing link gets a base |
|
South wall concrete reinforcement completed |
The 2 tonnes of concreting ballast didn't last long, more just in time deliveries required.
|
Dumpy bags anyone? |
End of day views...
|
Down side from the bridge, brickwork all wrapped up |
|
Cess bypass pipe back in and working |
That looks a hell of a job in Cheltenham. A fine blog and thank you.
ReplyDeleteI gave you all a cheery wave from the trains as I passed on Thursday (well I thought it was cheery anyway!). Marvellous work (you seemed to be the only ones on Thursday) one day i will understand why you have two large "Land Drain" type pipes one half the size of the other on the down side; is one to be dispensed with when all is done?
ReplyDeletePowli
Hi Powli, the 600mm pipe is the bit we cut off the inlet, it's heading for store when we get round to it. The 225mm pipe is a bit we are using to bypass the wet concrete, we had it out on Thursday while we pumped around the works. We have another 3 piles of pipe in the vicinity, 2 are for use on Culvert 11b, and the third pile is spare at the moment. Cheers, Stuart
Delete