Tuesday, 30 January 2024

Dry January

No, nothing to do with abstinence or not of alcoholic drinks in the first month of the year. But a statement on the weather. The first three working days for the team were entirely dry, and on the fourth the precipitation was just some early morning drizzle. (Or mizzle as the weather forecaster called it – it was more of a mist and low cloud). As the fourth Thursday of January was Burns Night – I am sure that one or two of the team enjoyed an after work tipple or three.

Thursday 18th January

The dry weather certainly has made a big difference. Some of the watercourses we inspected today were dry or just damp, this time last year some were noted as flowing strongly; and no sign of the standing water reported just before Christmas. However, the weather did give us one problem - frozen metal inspection lids on the inlets of cross drains 39B and 40B. Not surprising with overnight temperatures of -8C; but a combination of hot water, WD40 and brute strength managed to shift them.

With no wind and plenty of sunshine, our lunch break was longer than last week - and we had a stunning view west past the Malverns with the Welsh mountains just visible.


Opened eventually! Frost and ice still on the inside of the metal lid of 39B inlet.


Six of the team were in attendance. The work was the internal visual inspection and clearance of cross drains 39B, 40A, 40B, 41A, 41B and 41C between Bishops Cleeve and Kayte Lane. We also greased the 10mm bolts on the metal inspection cover in the footpath by Pecked Lane crossing at Bishops Cleeve. Also cleared was the remaining vegetation round cess chambers, mileposts and some other uprights which the robo fail can not reach. There are a few more of these to do - but these can wait until later in the year as this is strimming activities not brush cutting so can be done in bird nesting season and the better tool is a cord strimmer rather than a brushcutter.

 

For a cross drain, 40B is quite a drawn out structure. Here is where a stream enters the cutting on the down side, it comes from some springs up on Cleeve Hill. Some of the water runs in pipes down to the cess, but some runs south in a crest ditch. Where the cutting transitions into an embankment, this becomes a toe ditch; and the cess empties into it (see next photo). Finally it all runs into the inlet of the main 40B structure - over quarter of a mile from the stream entry. Quite why the GWR (or the contractors) built it this way is a mystery.
This is the little dinky headwall where the down side cess is piped into the toe ditch to run to 40B.

We noted quite a large amount of litter around Two Hedges Road, obviously tossed over from the footpath. A little further south were some larger items of non-railway rubbish inside the boundary fence. We removed some the bigger metal items.

Just before Christmas there was a pond here - all dry (well OK just damp) here now. This is the outlet  (up or Malvern side) of cross drain 41A. Downstream is the school playing fields, without a proper channel for this watercourse.

The wildlife spotters in the team were on the lookout for the visiting winter birds. A small flock of fieldfares were noted at Bishops Cleeve in one of the lineside back gardens. No sign of waxwings or redstarts though. As usual with clearance activities, it is the tame robins that come closest. Near Kayte Lane we even spotted one inside a cross drain bore.

Thursday 25th January

Headline activity for today was the completion of the 2023 programme of internal visual inspections and clearance of culverts and cross drains - the last two (as usually is the case) being those south of Hunting Butts on the disused course of the line.

Again the team size was six, and we appreciated the warmer temperature. Once the early morning mist cleared, it was a reasonable day. In places the ground conditions were noticeable dry – a consequence of a few days with no rain and a good drying breeze.

Initially all the team were involved with the recovery of 3 9-foot lengths of bridge rail from under Evesham Road bridge at Cheltenham Racecourse. We also recovered two concrete catch pit rings from near the siding point south of the bridge; and some various bits of metal scrap.

The only item moving on the rails south of Gotherington was our permaquip trolley. Here Ian provides the motive power heading south through Racecourse station. Coming back with three lengths of bridge rail and two concrete chamber rings required more effort!

Then three of the team headed off to culverts 44A south of Hunting Butts tunnel and 45A at Wymans Brook to undertake the visual inspections and the essential clearance. The brickwork of the outlet (up side) of 45A Wymans Brook has noticeably deteriorated as a stump of an ash tree is growing again. The other item of note was that the up side low mileage toe ditch that feeds into 44A outlet was flowing - probably from field run off as the field had just been ploughed. There was no flow in the up side cess chambers south of the tunnel, but as expected a steady flow in the down side and into 44A inlet.

Looking down the 'chimney' chamber on the down inlet side of culvert 45A at Wymans Brook. The brook is over 20 feet down; it is piped all the way back to the lake in Pritville Park. This the most southerly structure on today's GWSR.
 

The other three team members cleared vegetation from around all the cess chambers on both sides between Evesham Road bridge and Hunting Butts tunnel north portal. Good to report that all the anchored down blue mesh chamber covers are still intact. Hunting Butts does suffer from trespassers and vandals, so everything needs to be anchored down. On the south side of the tunnel there was evidence of recent trespass. We spotted a Deliveroo bag inside the tunnel and the burnt out remains of the Deliveroo tricycle on the old trackbed at the footpath crossing. Even with the dry days, water was still running of the down side field north of the tunnel. It runs into the cess drain and then out through the tunnel. There was some evidence of a significant flow during the recent storms.

In Hunting Butts tunnel, the two cess drains combine into a single drain that runs in the 6 foot. This is the lid of separation chamber on the south (high mileage) end. Firmly screwed down - a job we did several years ago.
 

After lunch the combined team cleared the access on both sides of the line to bridge 42A - the Hyde Brook watercourse. This is bridge and not a culvert, so the visual inspection is down to the bridges team. However it does look to be in good condition - one of the best on the line!

Outlet (up or Malvern side) of Hyde Brook watercourse - bridge 42A. One day all our headwalls will be this good!

Finally back at Winchcombe yard - the unloading task included finding a suitable spot for the lengths of bridge rail. The milepost replacement project will be restarting shortly.

Not a great deal to report on the wildlife front this week. There were plenty of slugs and woodlice under the loose coping bricks and in gaps on culverts 44A and 45A. We spotted a single black headed gull at Cheltenham Racecourse. The noisy flock of herring gulls around Cheltenham Spa (Landsdown) station do not seem to have ventured north – yet.



Monday, 15 January 2024

Fox on the run

Like many mainline and heritage railways, the route of the GWSR is a haven for wildlife, both animal and plant. Working outdoors on the line, which in places is well away from roads and human habitation, is a good opportunity to view the wildlife at close quarters. One of the members of the Drainage team is the primary author of the “Nature Between The Fences” page on the Railway’s web site. However, close up observation of most birds and all mammals suffers for two reasons. Firstly, apart from tea and lunch breaks we are too busy, often using machines which create some noise. Secondly we are wearing bright orange PPE – easily spotted by animals as well as the crews of approaching trains. Hence, good pictures of mammals and birds from our work sites are rare. Just occasionally we do get lucky.

Fox at Gotherington. [Photo by Dave]

Dave was able to capture this fox near Gotherington on our first work day this year. It was during morning tea break and the vehicle made for a reasonable hide. Not to be outdone, the other team that day had a visit at lunchtime from a felis catus (OK, not really wild life!); probably the smell of tinned fish from a lunch box was the attraction.

Thursday 4th January

A very productive day to start the year, and importantly there was no rain. However, underfoot conditions were very wet; storm Henk and the wet period over New Year has left a lot of water. Almost every watercourse we looked at was flowing strongly or even furiously. At Gotherington on the down (Cotswold) side there was a stream coming across the field to cross drain 35A with evidence of recent very strong flow.

Down (Cotswold) side at Gotherington. Normally there is just a depression in the field. Flowing water into cross drain 35A only happens in really wet weather.

The attending six members split into two teams of three for most of the day. Because of the ongoing Permanent Way work south of Gotherington loop, we revised our plans. A gap in the rails near the south points to the loop prevented use of a permaquip trolley from Manor Lane. Using a trolley from Gotherington Yard is strenuous – as there is a good uphill section. So to access the three cross drains by the loop (35A, 35B and 35C) we obtained permission to use the field of the adjoining garden centre. This reduced the amount of carrying equipment (and flasks for tea/coffee) considerably.

We don't have many red brick drainage structures. This is an exception, the under footpath entrance headwall for cross drain 35C. Strictly this is outside of the railway boundary, but we keep it in good order.

Between the teams, we completed the clearance and inspections of cross drains 35A, 35B, 35C, 35D, 36A, and 36B. We also cleared cross drains 37A, 37B and 37C south of Manor Lane.

Whilst at Manor Lane we inspected the roadside gulleys under bridge 36. Although flowing sufficiently to clear the water; one gully was partly obstructed with stones. As we did not have the finger grab with us, full clearance of this was deferred. Also at bridge 36 we measured up for an alternative scheme to replace the coping on the down (Cotswold) side parapet. Ideally this should use 16" coping bricks, of which we don't have any in stock. Instead we plan to use pairs of standard single bullnose bricks (BN1); which does involve some cutting. There is a good possibility that we will be donated a supply of imperial bullnose bricks which would be ideal for this project.

Up side parapet of bridge 36 (Manor Lane). Note how the 16" coping block overhangs the outside face but not the inside. We plan to make the down side parapet appear similar.

Apart from the mammals reference earlier, noted wild life was mainly birds. Three species of raptor (kestrels, red kites, buzzards); robins and several unidentified LBJs (little brown jobs).

Thursday 11th January

Another dry day – so far 2024 is so much drier that 2023. However, it was cold. Not too cold to work, but our lunch break was certainly shorter than usual! The seven team members attending found to keep warm meant to keep working!

Main task for the day was to complete the culvert and cross drain clearance and inspection between Manor Lane, Gotherington and Pecked Lane, Bishops Cleeve. This was helped by already having cleared cross drains 37A, 37B and 37C last week and the Saturday clearance team having cleared the down side at 38A (the up side there is not accessible). Hence there was 9 visual inspection reports to be written and reviewed. (cross drains 37A to 37G and culverts 38A and 39A). 39A is the one by the foot crossing at Pecked Lane. Here we were able to remove the metal lids of the manhole in the footpath so were able to clear out most of the debris which had collected where the outflow from the railway property divides into two concrete pipes.

The intermediate chamber of cross drain 37D by the foot crossing between Gotherington and Bishops Cleeve. This is bore under the track; there is then another pipe under the footpath.

One of our larger culverts, 38A. This is by the mobile home park at Woodmancote. Flood alleviation work, including some 'leaky dams' has meant this does not get overwhelmed by flood waters now.

39A at Pecked Lane crossing. Opening the metal lids in the footpath reveals where the exit from railway land by the houses splits into two concrete pipes. And this is where a build up of debris occurs - at least mostly leaves and small twigs. When we open up these sort of manholes we use our gas detector to check the levels of carbon monoxide; carbon dioxide, hydrogen sulphide and other nasty gases.

Pleasing to note that we found no significant deterioration of the inspected culverts and cross drains. Just a lot more water flowing into and through them, and evidence of deeper and faster flows in the preceding weeks. Additionally clearance of the up (Malvern) side embankment by our contractor with his robot flail has enabled us to spot a couple of damp patches. These are between milepost 16¾ and bridge 38; and are probably as a result of the wet autumn and early winter. The downhill drainage here is minimal, the ground is quite flat. No doubt this is why it is a prime spot for new houses.

At the beginning of the day we tackled three odd jobs at Gotherington. First we replaced the broken lids on the outlet chamber of cross drain 36B, a casualty of the robo flail.

New lids and marker posts for 37B up side. [Photo by Roger]

Second, we completed the clearance of the road gullies under bridge 36 using the pronged grab; the offending material being medium sized stone.
Not quite wildlife at Manor Lane. This does show how the road dips under the bridge. This is one where there is no alternative road access if blocked drains makes the road impassable. (No this was not a photo from January!)


Thirdly, mile post 15¾ by Gotherington loop was reset and the bridge rail post cemented into position. It no longer leans at an alarming angle away from the track. We will repaint the bridge rail and replace the BR style yellow metal head in due course.
MP15/III (to use it's structure id) concreted in place at the correct lateral angle and square longitudinally. [Photo by Roger]

Finally back at Winchcombe we inspected the up side low mileage wing wall of the River Isbourne bridge (21A). Repairing the displaced coping stones and first few courses of bricks is within our capabilities - it will need at least one replacement 18" bull nose coping block. This is likely to be one of our first tasks following the completion of the culvert and cross drain visual inspection programme. It does, of course, depend on dry weather and normal river levels. And no other urgent tasks cropping up!

Nothing new or unusual on the animal or bird front for our wildlife report this time. One noticeable item is the large amount of mistletoe on the trees between Gotherington and Bishops Cleeve. We should have worked on this stretch before Christmas to enable some to be harvested for decorations!

Mistletoe near Gotherington. We will take orders for next Christmas!

Finally, the easing of the wet weather has allowed our contractor to complete the infilling of the 11B to 11A up side diversion ditch at Stanton. So at last our major project of 2023 is complete! Well almost! We may have to raise some of the inspection chambers by one or two rings as they are now flush with the ground unless the ground compacts and shrinks. Ensuring that inspection chambers stand clear of vegetation does help prevent close encounters with robo flails, telehandlers and other road vehicles.

River Isbourne

One of our regular readers has asked for some pictures of the flood alleviation work that Walsh completed on the River Isbourne at bridge 21A. So here are some – including a 'before' picture of the wing wall that we will be working on.

Down (Cotswold) side, or upstream. Pipe inlet at top right comes from the stream which runs behind Winchcombe Yard and under Churchward House compound.

Down (Cotswold) side showing inlet from embankment toe drain.

Down (Cotswold) side portal.

Up (Malvern) side low mileage wing wall - the end of which which we will rebuild.

Up (Malvern) side, or downstream.

Up (Malvern) side showing the outfall of the cess drain that runs between the platforms at Winchcombe station then through the deep man hole by the Usk weighbridge building and then alongside the boundary fence.

 

Sunday, 24 December 2023

Another year over

As one year draws to a close and new one beckons, the current convention is for publications to publish a review of the year. So the next paragraph is our short review of 2023.

Wet.

Strictly not wet every day or even every working day. However, with the rainy and unsettled period in the summer (coinciding with the school holidays from mid July to end of August) and the early autumn storms, just wet seems an apt summary. Few people will remember the fine, sunny, warm spells which we did experience; particularly the mini-heatwave at the beginning of September.

One advantage of such wet spells is that we can see how well the railway’s drainage system is working, and where the bottle necks are.

I hope you have enjoyed reading our posts this year. Wishing you all Season’s Greetings and have a healthy, peaceful and prosperous 2024. And join me in asking Santa for more drier weather next year.

Thursday 16th November

Contrary to my introduction to this post, for the first time in a number of weeks we had a working day with no rain.

Roger, Martin. Stu and Ian were attending a brush cutter operative course provided by Greenway, all achieving the LANTRA qualification. The course also covered user maintenance, and as a result we are making some changes to our procedures. This should reduce the visits to a Stihl main dealer to once per year per machine.

Dave, Nigel, Jonathan and myself had a varied and productive day at a variety of sites on the railway. First of all was the raising of a crest chamber on the down side between Winchcombe and Greet tunnel. This had been hit by Tom Clark's robo flail. Four additional concrete rings were added - the vegetation will have to grow a lot to obscure it now. The other crest chambers towards the tunnel were checked - all will need raising, but only be one or two rings.

Raised crest chamber on down side between Winchcombe and Greet tunnel.

Second item was to Stanway viaduct to collect some material that Walsh had surplus after constructing the set of steps on the low mileage end of the down side. This consisted of different lengths of galvanised tube and substantial timber boards; plus handrail fittings. These are now stored - they will be ideal for making some headwall safety handrails or makers.

Stairway to Heaven? No - the new steps to Stanway viaduct down side low mileage end.

Walsh's progress on the viaduct (as of 16 November); just after the extra work on the parapet was discovered.

Third item was to continue with the culvert/cross drain internal visual inspections and clearance. Cross drains 25B and 25C which were cleared last week were inspected. Cross drain 27A and culvert 27B south of Gretton were cleared and inspected. On the later two there was significant vegetation growth on the down side alongside JJ Farms. Very apparent how much more water there is this autumn. This is making photographing the inside of the culvert bores difficult or impossible in some cases. Perhaps we need to invest in a selfi-stick! Photo of culvert 27B up side (below) was taken by reaching down from the headwall.

Looking into culvert 27B from the exit end (up side).

On the way back from Gretton we stopped at Prescott Road bridge (32) for a quick inspection of culvert 31B. Following the work earlier this year on the exit to the roadside pipe/ditch this is flowing much better. Clearing the build up of debris on the grill to the roadside pipe and racking out some reeds from the pit increased the flow even more - essentially no standing water in the pit.

Culvert 31B outlet, the entrance to the roadside pipe, Prescott Road. Just needs some replacement fence.

Finally near the Tirle Brook culvert (32A) we found a cess chamber which also had had a close encounter with a robo flail (or was it the telehandler?) We reset the displaced top concrete ring. It will require a further visit to add another ring on top and to fish out the heavy thick lid which has fallen into the chamber. Despite these chamber hits, the robo flail provides some impressive results - picture below shows the cleared up side embankment at Working Lane.

Working Lane showing the cleared embankment on the up side low mileage end of bridge 25. Amazing what a robo flail can do!

Wildlife report (all Gretton)
Rabbits - with quite a bit of evidence of burrowing mainly on the down side cross drain 27A and culvert 27B.
Kestrel.
Woodlice - underneath a toe ditch slab, which was useful to show that this was just damp and not flooded.

Thursday 23rd November

Just a small team of four (Nigel, Martin, Dave and myself) working on drainage items - plus another two members of the team involved with the accident exercise (Jonathan as a casualty and Roger as first responder). At least this meant we could comfortably fit into one vehicle.

First item was to measure the ditch in Winchcombe Yard behind the site of the new S&T building. This is to get accurate estimate for quantity of concrete canvas to order; this to make the ditch water tight from the exit from Churchward House to beyond the new S&T building.

Then out to Gretton for the main tasks of the day; clearance and visual inspections of cross drains 27C, 28A, 30B and culvert 30A. The good news is that there is no obvious deterioration in these structures. What is obvious is the vegetation growth this year has been more than last year; and that all the water courses are flowing faster or deeper - apart from 28A inlet. (Picture below shows the small dribble entering the inlet chamber).

Inside the entrance chamber of cross drain 28Aon the down side at Stanley Pontlarge. Input from the stream brings plenty of sand and gravel which eventually collects in the outlet chamber several hundred yards away.

At cross drain 28A we removed a lot of sandy silt from the exit chamber (by the roadside entrance to the small holding). At culvert 30A we created a new access from track level to the boundary fence of the private road which runs under bridge 30. This is on the down side high mileage end. This embankment is steep here - there are sudden drops nearer the bridge and all four wing walls of the bridge are high and narrow and have no fences. The new access terminates at one of the headwalls of the down side toe drain that runs between cross drain 30B and culvert 30A. This would be a sensible site for a new set of steps such as that at Stanway Viaduct.

The new access route by bridge 30, down side high mileage.

Then it was on to Prescott Road bridge to measure up for the replacement fence sections around the exit of culvert 31B.

Finally at Dixton cutting just on the low mileage side of the Tirle brook (culvert 32A) we recovered the thick heavy chamber lid from the cess chamber which the robo flail (or telehandler) had hit. We also raised the height of this chamber by one additional concrete ring.

Dixton cutting up side cess chamber - raised in height but still using the heavy (BR or even GWR era) thick lids.

Wildlife report
Being a sunny day there was plenty of bird activity. Raptors in particular, we spotted a red kite, a buzzard being mobbed by crows, and a kestrel who appreciated the clearance of 30A improving visibility of small mammals from his perch on a dead tree. There were lots of pheasants on the lineside (and in the four foot) undisturbed by trains.

Thursday 30th November

Certainly the coldest day for a long time and almost a full turnout (8), the best for a couple of months.

First an unplanned job - to fix yet another cess chamber that had had a close encounter with either the robo flail or the telehander or one of the road vehicles. So Roger, Jonathan, Stuart and I headed to Chicken Curve where we found the chamber where the up side cess drains off to cross drain 20B at 11m35c. Two lids were broken; so as a temporary repair these were removed and a blue mesh grid placed on top weighed down with the one unbroken lid.

Meanwhile the other four (Ian, Dave, Nigel and Martin) had headed to JJ Farms Bridge to commence the internal inspections and clearance of cross drains and culverts for the day. First off was cross drain 31A. Then on to Prescott Road bridge where the other four arrived to tackle culvert 31B. Here the operation was recovering the sections of red barriers which were the temporary fence and to erect a new section of roadside fence and restore the railway boundary fence which runs over the new sandbag headwall of the roadside pipe. The roadside chamber on the inlet side (down side, low mileage) was cleared and inspected - significant amounts of Hydrogen Sulphite detected. The source of this was traced to foul water in the roadside ditch on the other side of the road (high mileage); this flows into a small pit together with the (dry) down side high mileage toe drain, then under the road to the chamber. Source of the foul water is outside of the railway boundary - we reported this to Severn Trent (which took some effort!).


All done at culvert 31B, Prescott Road, with the new sections of fence.
 

Then on to culvert 32A, Tirle Brook flume culvert in Dixton Cutting and finally after a short lunch break cross drain 33A and culvert 33B at Gotherington Yard. All required significant vegetation removal, otherwise no apparent deterioration in condition. One exception is a chamber by the down side boundary fence on the toe pipe leading to culvert 33B. This needs a course of bricks replaced by a concrete ring or two and a new lid (or blue mesh). Also there is a small tree growing on the line of the pipe which needs needs removing - a job for our chain saw operatives, probably after Christmas.

Jonathan and Dave clearing out the inlet (up side) of Tirle Brook flume culvert 32A. Fortunately although the flow was fast, it was not deep.

A lovely small and neat outlet headwall - and in good condition. Culvert 33B at Gotherington.

The inlet of 33B is on the west side of the road, one of the few headwalls constructed from stone (or fake stone) blocks. This is just inside the railway boundary of the triangle of land forming the high mileage down side wing wall of bridge 34.

Thursday 7th December

Unlike last week, this week saw only a small team of five. So we did not split into groups. Additionally to avoid a soaking in the afternoon, we finished outdoor work at lunchtime. The afternoon was indeed one of the wettest this year.

First we headed to Stow Road Bridge (13) at Toddington to investigate raising the down side cess chamber. We cleared some of the silt that comes from under the side arch of the bridge during heavy rain. Then measured up for plan A, which is to add a concrete ring modified to pass the S&T cables underneath. The S&T cables run directly above the existing grill. Then with a metal or blue mesh cover; the chamber will be at the same height at the S&T trunking enabling additional ballast to create a better walkway as this is right by the uncoupling point for 7 coach trains. Unfortunately checking against a concrete ring has meant a move to plan B. The cutout to clear the S&T cables would completely wreck the integrity of the concrete ring.

Down side cess just by Stow Road bridge at Toddington showing the two issues. (1) S&T cables passing over the top of the grill. (2) Plenty of silt washed down the cutting side from the road above.

Next was the continuance of the culvert/cross drain clearance and inspection programme. The first one this week was cross drain 14A - no need for clearance here as the Wednesday clearance team have done a splendid job all along the down side fence from Toddington Signal box. What we did need to do was to reset the top five concrete rings as these had become displaced and unstable. This was not an easy option with several inches of potentially foul water in the ditch. We applied our additional PPE and disinfectant procedures when dealing with potential foul water.

Cross drain 14A, stack of rings on the inlet rebuilt. This is in the long ditch that runs all the way almost from Toddington Signal box to Didbrook No1 bridge.

Then on to culvert 14B. Another good job by the Wednesday gang meant the down side access was already clear - so we just had the up side to clear. The up side exit pond here is currently very deep, we estimate at least 8 inches, and water is flowing fast out of the pipe under the adjoining land. Hence seeing what is happening on the high mileage wing wall was not possible. Finally onto culvert 15A - also flowing very fast. This will need a visit when the water has subsided to reset the concrete slabs on the low mileage side of the entrance channel.

Culvert 14B outlet - there is a small wing wall but the deep water makes inspection impossible!

Finally just before the afternoon rains set in, we added two concrete rings to the up side cess chamber near cross drain 20B on Chicken Curve. This was one of those damaged by a vehicle (or the robo flail) - it now has a blue mesh lid so should be more visible. The wrecked concrete lids were recovered to the rubble pile in Winchcombe Yard.

Chicken Curve up side cess chamber fixed - raised and mess lid added. All fixed even before the defect report reached the team!

In the afternoon in the comparative dry of the Estates Management container in Winchcombe Yard we spent some time performing preventive maintenance on some of the brush cutters. At this time of year, some of these machines get considerable usage on Thursdays and by the clearance teams on Saturdays and Wednesdays.

Wildlife report
Most wildlife was sensible not to venture out in the rain. We did however get a very close look at a kestrel on the power lines at Didbrook; and disturbed some pheasants on the up side.

Thursday 14th December

With seven team member attending and a dry (even sunny in the afternoon) day we achieved more than the work plan!

Culvert and cross drain visual inspections and clearance covered 16A, 16B, 16C, 18A, 19A, 19B, 20A, 20B and part of 20C. That is from Didbrook No 2 bridge (16) down to Chicken Curve. We also cleared the roadside gullies under Didbrook No 2 bridge - this is where some of the flow from the down side high mileage cess which does not go into 16A empties. During the rains over the previous weekend the road under the bridge had very deep puddles.

By the roadside on the down side high mileage of bridge 16 is where some of the cess drains flows out and into a roadside gulley.

Plenty of blue paint on the lids of 16B outlet should make this more visible.

Our clearance also covered all the cess chambers, mileposts and HP gas main markers on this section. In most cases this was the last few inches that our clearance contract’s robo flail can not reach.

Cross drain 19A is another one of our small and neat structures. There is no stream at this point, so the pipe is essentially to route the down side cess and boundary water to the up side and then off to the adjacent field. In dry years we see no water here!
 

A gulley drain in the farm track under Old Farmers Accommodation Bridge (20) also cleared - this reduced the standing water under the bridge.

Three of the team undertook a second inspection of the down side cess chamber intermediately under Stow Road bridge (13) at Toddington. This was in order to develop plan B, after determining that cutting slots into standard concrete chamber rings was not going to be feasible to raise the height the chamber without moving the S&T cables. Increasing the height with brick courses will need 120 bricks - and is a couple of days work. So perhaps we move to plan C – using GRP catch pit rings which are quicker to install and easier to cut the slots required for the S&T cables.

Wildlife report
Plenty of robins attracted by the cleared access points to culverts/cross drains.
Large flock of birds noted performing murmurations over towards Wood Stanway - but too far away to determine if starlings or fieldfares.
Rabbits at Hayles Abbey.
Voles at Didbrook.

Thursday 21st December

Another week with last minute reduction in the team strength to five. So we had to re-plan the work as the original idea was three groups. (A very valid excuse from our chief first responder, Roger, he had to cover a last minute gap in the first aid team for the Santa trains at Winchcombe.)

First task for the two early arrivals was to use the telehandler to extract the final stack of concrete catch pit rings from the items at the back of Winchcombe yard. This had to be accomplished early as the yard became full of parked Santa helper's cars by 9am. Six of the rings were then taken to the down side crest between Winchcombe Greet Road bridge and the low mileage portal of Greet tunnel. Five were used to raise the height of two crest chambers, the sixth was placed ready to be used when we construct a proper chamber on the end of the crest pipe. The opportunity was take to inspect the crest pipe - it was flowing well, it picks up two streams and some land drains. In the final crest chamber where some of the flow diverts down to the down side cess (and then runs through the cess drain in the 6 foot at the station) we removed a partial blockage of vegetation. We now only have three concrete rings left in stock - our intention is in future to use GRP rings as these are far easier to handle.

Martin, Nigel and Dave contemplate the options for building a chamber at the down side crest pipe entry close to the south portal of Greet Tunnel.

On the way back from the crest we stopped to watch the first Santa train arrive at Winchombe. Normally we get a few waves from passengers - but with this train of excited children on the way to meet Santa we had a wave from every passenger. Maybe one or two of them will be the next generation of volunteers.

Two team members also ventured to Chicken Curve to complete the clearance and internal inspection of cross drain 20C. Water from the balancing pond in the down side orchard is trickling into the inlet here - the stream is running well. We discovered that there is a gap on the outlet (up) side inside of our fence so we could see that the flow in and out the bore is equal. Fortunate as looking into the bore from the down side shows there is something stuck in it. So we will have to return when the water level is down to attempt some rodding out. But this gives and excuse for our Christmas Quiz - what is it that is stuck in the bore? Picture below. We will reveal what the mystery object is when we extract it in the New Year.

What is that oblong shape partially obstructing cross drain 20C? Hopefully we will find out next year.

The last Thursday before Christmas does mean we have service trains to watch. Foremarke Hall runs over Chicken Curve light engine to Winchcombe to take the second Santa ECS to Cheltenham.

Then up to Stanton Aqueduct (bridge 9). The plan here was to seal the cracks in the down side concrete inlet and between it and the trough foundation with some flexible mastic sealant. However this does require the crack to be clean and dry - it was certainly not dry. Although the water from the stream is running in through the pipe and then right through the trough - there was signs of dampness in the cracks. Again, another task to reschedule for the New Year, with either a method to dry out the cracks or with some sealant which can go down wet. On the up exit side of the aqueduct we cleared the grill on the exit pipe into the adjoining field - this was well clogged with twigs and leaves.

Grills like this one on the exit of the aqueduct stream to the adjoining field do stop large objects from entering the pope. However they get obstructed with leaves and twigs, so regular clearing is needed.

Whilst at Stanton we took the opportunity to inspect the 11B to 11A up side diversion we constructed earlier this year. The real good news is that this is working well - there is very little standing water on the down side in the adjoining field; the low mileage inlet to the 11B bore was running slowly; flow in the new up side pipe was steady and increasing towards the exit into the 11A ditch. This suggests it is collecting water from the old land drains - good news for the toe of the embankment. Also good news is that there is no standing water at all on the up side, either on our side or our neighbours side of the hedge.

The pipe at the top of the picture is the outflow of the 11B to 11A up side diversion - flowing well. The second pipe on the left is from under bridge 11, and the main flow at bottom is culvert 11A.

Just a small stretch of standing water in our neighbours field on the down side at cross drain 11B. Earlier this year this was a large lake - so although we have only completed the up side work at 11B, the results are already noticeable.       

As we were at Stanton, we took another peek at the work on Stanway Viaduct. The appeal for funding is still open, if you have not donated yet then please do so. Click this link. The additional work to secure the parapets has added to the cost of repairs.





Finally some pictures of the good work Walsh are doing on Stanway Viaduct. The first stage of the extra work to stabilise the parapets is complete and the first of the horizontal retaining rods at the end of the viaduct is in place.



   


Back at Winchcombe we completed the day with some more machinery maintenance; fixing a problem with a brush cutter reported by the Wednesday clearance team.

Wildlife report
Chicken curve: Herons
Stanton: Deer (probably roe, not rein as none had red noses); Red kite, Buzzard, Kestrel, crow, hibernating queen wasps (in discard child's jersey)

About the only time of the year when taking close up pictures of wasps is possible.

Winchcombe station: Penguins (very tame and of a strange species which can sing in English!)