Thursday 20th February
Two teams of four working at two sites with two diggers, but both of those were at one site.
Dave, Nigel, Peter and Polly headed to Little Buckland Bridge (5). The main task was to clear overhanging trees and undergrowth from the path of the outlet ditch of cross drain 5A. This runs along the border of a triangle of GWSR land on the high mileage end of the up (Malvern) side of the bridge. Outside of the railway land, this then becomes a roadside ditch; or rather it should! The roadside ditch is very overgrown and shallow; and all the water discharging from 5A seeps into the ground. With the improvements to the drainage on the down (Cotswold) side of the line; 5A is likely to take a greater flow. Hence the need for ensuring it can effectively drain. Today we just scraped debris from the ditch on the railway land; further deepening it can only happen when the roadside ditch is improved. There is a temporary dam in the toe ditch on the down side which is diverting some of the flow to run south to cross drain 5B. This is to ensure that the 5A outlet ditch does not overflow onto Little Buckland Road, this causes deep puddles under the bridge.
5A outlet headwall with Polly & Nigel clearing access to the fence. [Photo by Dave] |
Looking back up the ditch to the railway - Peter just visible. Water now flowing after some minimal cleaning of the ditch. [Photo by Dave] |
Beside clearing access to permit later ditch deepening, the team checked and cleaned the roadside gullies under the bridge.
Our other four workers, Jonathan, Martin, Roger and Andrew, headed in the opposite direction to culvert 24A opposite the Royal Oak at Gretton. Here they were joined by Mark with a 8-tonne excavator from our contractor, Tom Clarke. The task of the day was to fill in the hole around the new chamber in the outlet of 24A between the track bed and the haul road.
First we used some large stones which we had brought from Winchcombe. This was followed by the material which had been excavated a few weeks ago, and finally several tonnes of spent ballast. The spent ballast had come from the Didbrook relaying on Wednesday, again courtesy of Tom Clarke with a tractor and trailer. One pile of ballast was at the top of the haul road; the second at the bottom. Jonathan used our telehandler with the bucket to bring the material up the haul road. Or most of it, as some was required to fill in some deep ruts on the haul road itself. At times this operation was like a ballet for two diggers; telehandler dumps material then the excavator nimbly moves it into place and compresses it down. The caterpillar tracks and the weight of the excavator were used to good advantage to compact the infill forming the reinstated vehicle access on the vacant trackbed on the up (Malvern) side.
First into the hole was some medium size stone - left over from the Rive Isbourne gabions. Note the Royal Oak pub in the background, at 9am there was a delicious aroma of breakfast wafting across! |
Next Mark reinstates the infill that was excavated a couple of weeks ago. |
The bucket of the excavator is used to carefully compress the infill. |
Spent ballast from Didbrook is placed with the Telehandler. |
A coordinated ballet for two diggers! |
Mark levels out the last of the spent ballast. |
By just after lunchtime the infilling was complete. We removed all the temporary barriers; and fitted brackets to the blue mesh lid on the top of the new chamber.
Job done 1 - from the vacant up side track bed. |
Job done 2 - looking towards Gretton from the haul road. |
Job done 3 - looking towards Gretton from the vacant up side track bed. |
So structurally the rebuild of 24A is now complete. There is plenty of scope for using more spent ballast and the infill from Broadway platform 2 for landscaping the area between the culvert and the top of the haul road to give a more gradual slope to the embankment. Plus we have two items to complete. First we will obtain and install one more GRP chamber ring to make the chamber well proud of the uphill embankment line. Secondly we will replace the old sleepers we have placed at the edge of the vacant trackbed with permanent safety markers to prevent vehicles leaving the vacant track before the top of the haul road and thus damaging the chamber.
With the bucket fitted telehandler at Gretton, we (well Jonathan and Martin mainly) took the opportunity to tidy the parking area at the bottom of the haul road. This has made the parking area a bit larger and is a start on our project to improve the drainage there. As a bonus, we recovered two lengths of bridge rail from the pile of debris. Although these were one time fence posts, we can remove the corroded sections for reuse as milepost uprights. So we took them back to Winchcombe to join our bridge rail stockpile at the far end of the wooden shed.
Wildlife report: Whilst the weather was much warmer (the warmest Thursday of the year so far); it was far from spring like! Frequent heavy showers and longer spells of rain – but a few brief shafts of sunshine. A welcome sight was some snowdrops flowering alongside Working Lane where a few years ago we improved the outlets of culverts 25A and 25B. The resident robin at Royal Oak welcomed us with plenty of song; but some pheasants soon scuttled away when we started work. At Winchcombe, the local Red Kite was circling very low above the yard; no doubt there is plenty of small mammals hiding amongst our stacks of materials.
UK Plant Operators Magazine YouTube Video The YouTube video shot by UK Plant Operators magazine of the excavation operation at 24A (16th January) is now published. The link is https://youtu.be/7-untMqWyOc?si