Tuesday, 3 September 2024

Summer is over

As we work outside during daylight hours, we adhere to the meteorological definition of summer (months of June, July and August), rather than the astronomical definition (the period between the summer solstice and the autumnal equinox). So this is the last report of this summer!

Thursday 8th August

A full complement of nine team members working, hence we split into three teams.

Nigel, Polly, Stuart and Ian progressed the bricklaying of the new inlet chamber for cross drain 11B at Stanton. Around 150 bricks were laid, three courses. It is likely to need two more days of brick laying here, this is turning out to be a deep structure to ensure stability of the embankment. The joint in the bore between the new plastic extension and the original SGP was cleaned from the inside.

The 11B inlet, this shows the unusual plan section. And the soon to be redundant old supermarket basket which had been in use as a grill.

Dave, Roger and Martin attended to the rebuilt of the down side crest chamber immediately adjacent to the low mileage end of bridge 10 at Stanton. Only one course of 36 bricks, all the removed bricks were reused and a new stub pipe entry added to catch water coming from the road was added. An attempt to rod out the outlet pipe between this chamber and the down side cess chamber was made; but there is quite a solid constriction of limescale about 1m up from the cess. We will see how this pipe behaves when the wet weather returns.

Rebuilt with all the original bricks, but a new inlet for road run off.

Jonathan and Andrew completed a few odd jobs. First a visit to Toddington to deliver five blue mesh catch pit covers to Walsh construction for use on the reinstated crest drain on the up side at Toddington North cutting. They also took the opportunity to remove several old wooden pallets from Winchcombe yard to the steam loco lighting up stack.

Our first use of the new blue transit (LBT - large blue transit to us, the other, older one is SBT for small blue transit). Toddington Steam Loco lighting up stack.
 

Then to Townsend Farm down side at Gotherington to inspect the recently rediscovered end of the toe drain. The clearance teams have cleared the fence line alongside the farm, which was where plastic twinwall pipes replaced the original cast iron pipes in the toe drains. These connect cross drain 27A and culvert 27B. Probably this was done in the 1990s - the high mileage end of the new pipe is an open connection to the old cast iron pipe and also allows inlet from a field boundary ditch. Now this join is accessible again, we will include it on the annual inspection and clearance of 27B.

Open connection between old and newer toe drain pipes by Townsend Farm. Maybe one day we will rebuild this with a proper chamber.
 

Next was a quick visit to JT Vehicle Services to get the tow hook on the new blue LWB transit raised - this to ensure that it does not catch on some of the steep slopes used to access the lineside. Finally they joined the groups at Stanton to unload aggregate for the back fill at 11B.

Wildlife report: Several rabbits that are afflicted with myxomatosis at Gotherington and Stanton; roe deer at Stanton. Plenty of fruit noted - apples, pears, plums and blackberries. However, all apart from some blackberries are not yet ripe enough.

Thursday 15th August

Six of the team attending, but only five working on drainage projects. Jonathan was attending a 360 mini excavator proficiency refresher class.

Sorry no pictures of the works due to a technical problem with the author’s phone - it took the pictures but then failed to save them or up load to cloud storage.

Nigel and Polly headed straight to Stanton down side 11B inlet, to continue the building of the walls of the new inlet chamber. Almost 200 bricks laid, so the walls are now complete except for the top course of bull nosed bricks.

Dave, Martin and Andrew first reinstated the heavy lid on the down side crest chamber immediately on the low mileage side of Stanton Road bridge (10), thus finishing off the repair here. They tested the exit from this with 10 litres of dye coloured water - but this did not reach the cess chamber. Hence the obstruction discovered last week is quite substantial. Next they started the 2024 culvert & cross drain clearance and internal visual examination programme. Culvert 11A was cleared and inspected, and the up side 11B to 11A diversion chambers were cleared of surrounding vegetation.

After lunch all five completed a request from the farmer of the adjoining fields to clear the full width of Gallery Farm crossing. This is to enable wide farm machinery (combine harvesters) to cross the line. Most of the vegetation was bramble - but also some tall grasses which were preventing the high mileage gates from opening. In the undergrowth on the up side of the crossing was the remains of the cattle grids which were removed by PWay last winter. These are now stacked vertically so to not impinge on the width of the crossing. We noted that the down side low mileage gate post of the crossing is rotten at the base, so this needs the fencing contractor to replace.

Gallery Farm crossing at Stanton, full width cleared. (Photo taken 22nd August).
 

Finally back at Winchcombe we found suitable lengths of scaffold tube to form the safety fence of the new 11B inlet. The uprights of these will be installed next week.

Wildlife report: Evidence of deer at Stanton. The small plums on the trees at Stanton yard entrance are still not fully ripe – they will need quite a few more warm sunny days. The sloes in the hedges are far from ripe, all very hard. So too are the Stanton pears - but these are perry pears and will stay rock hard even when they drop off the trees in October. We noted a covering of the pink flowers of Convolvulus arvensis (field bindweed) particularly near bridge 11.

Thursday 22nd August

Another day with a full complement of 9 team members - hence the need for 3 vehicles to transport everyone plus tools and materials to site.

The site was of course Stanton, mainly the down side inlet of cross drain 11B. Following delivery of the last required aggregate and bull nose bricks, we returned the dumper to Winchcombe yard. Jonathan cleaned and serviced it. Nigel, Polly, Ian, Stuart and Roger concentrated on the prime task of concrete backfilling of the walls adjacent to the embankment. Three of the four uprights for the safety rails were inserted into the concrete. Some of the final course of bull nosed bricks were laid. A start was made on clearing back the boundary hedge to enable ditch digging to commence next week.

11B inlet concrete backfill.

First three uprights for the safety rails.
 

Meanwhile Dave and Martin worked on clearing the access and ditches of culvert 11C, enabling Andrew to under take the internal visual inspection. Also they cleared the down side embankment around the slip marker posts - all appear to be in line and upright and there is no signs of recent earth movement. Andrew also revisited culvert 11A and the up side chambers of the 11B to 11A diversion to re-take photographs for their internal visual inspections.

Culvert 11A has a bore than runs alongside the farm track under bridge 11.

Culvert 11C was extended on the down (inlet or Cotswold) side several years ago. Like many undertaken at that time, no headwall was built.

In contrast, the 11C outlet on the up (Malvern) side is the original GWR brick headwall. Just to prove that summer 2024 was not all wet, this culvert was bone dry at the time of inspection.

Also bone dry was the first chamber of the 11B to 11A up side diversion we constructed last year. This is the exit from the bore under the track.
 

Work after lunch was somewhat disrupted due to the gas main fracture on the B4632 leading to the road being closed between Toddington roundabout and Stanton Road. All the team spent some time pruning the overhanging trees on the entrance to Stanton yard. A lot of these are plum trees - and most of the fruit is now ripe. Most of the team went home with some of the fruit.

Thursday 28th August

The blog author was in Killybegs, once the western most terminus of the County Donegal Railway. No trace of the railway now remains in the town. Roger provided the following notes of today’s work.

Six of the team in attendance to progress a number of jobs all in the Stanton area.

We completed the hedge clearance on the downs side low mileage of cross drain 11B, this now enables access for the mini digger. This was brought to site and Jonathan commenced digging of the new (or rather instated) boundary toe ditch.

On the new 11B inlet structure (it is a combination of a chamber and an embankment retaining wall) the final bricks in the header courses were laid. A further intermediate bar to the safety handrail was added.

Almost complete, the new 11B inlet chamber. All bricks laid, and blue mesh lids cut to size. Just some earth backfill to add, and one more safety rail. Oh - and painting the safety rails. But what colour? Should we go for bright yellow as per Network Rail safety guide lines, or white, or silver, or GW light stone? [Photo by Dave]
 

Brush cutters were in action all day to clear the ditch which runs on the up side from culvert 11A back to the cess outlet. Also cleared were the three crest chambers and the ditch collection pit on the down side between bridges 10 (Stanton Road) and 11 (farm accommodation under bridge). Finally, all the cess chambers between bridge 11 and Stanton aqueduct (bridge 9) were cleared. Well almost, the very last one before the aqueduct escaped treatment as we ran out of 2-stroke petrol. A brush cutter in full cry is a thirsty beast!

No comments:

Post a Comment