The North Pole that is. Over the past few weeks the focus of our work has been on the Toddington to Winchcombe section. The normal routine is to drive along the track bed north from Winchcombe, then back from Toddington along the public roads. Thus we circle Winchcombe station, or the North Pole as it is known for the Santa trains season.
Thursday 17th November
A great boost to team productivity today. Not only all 7 team members in attendance; we had three working heavy duty brush cutters after their return from repairs and servicing. Consequently we were able to complete the clearance and visual inspections of 6 culverts and start work on a 7th.
First task for a team a three was to head to Southam Lane to investigate the cess drains. Just north of the bridge is an area which has a wet bed and the rail joins are ponding. This has been in this condition for several years. PWay are relaying it this winter; we had been asked to check to see if any leakage from the cess drains. The team inspected the manholes adjacent to rail lengths 12 and 13; they found no evidence of leakage from the cess. A couple of years ago the drainage on the down side under Southam Lane bridge was improved to handle what we think is run off from the road. This is working well, the area has not flooded since.
Down side cess chamber on low mileage side of Southam Lane, with pumping rail joint in background. [Photo by Dave] |
The culvert inspections and clearance started at Chicken Curve with 20C and worked northwards (towards Toddington, or in the up direction), so thus 20B, 20A, 19B, 19A, and 18A. Finally undertook some clearance of culvert 17B, the big one. The bridges team have already inspected that one; and most of the stream side growth is outside GWSR land. Occasionally we do cross the boundary to fix problems, for instance at 20A we cleared some obstructions from the outlet ditch (up side. This resulted in water dropping a couple of inches.
Outlet (up side) of 20A showing extension pipe and tide mark where the water level dropped after clearing the exit ditch. |
Looking inside 20A you can just see the old headwall; the extension plastic pipe is only a couple of feet long. |
We took the flail and were able to widen the vehicle track (old up side formation) for most of the length from Winchcombe down home signal to New Farmers Accommodation Bridge (19). The flail does need servicing - reverse is hard to engage as the cable for that gear is fraying and is at the limit of adjustment.
Also by taking sand and cement we were able to attend to some of the minor repointing and resetting tasks. These included 20B down cess outlet and 19A down side headwall.
19A is one of the smaller cross drains; down side headwall after the minor repointing attended to. |
At bridge 20 (Old Farmers Accommodation Bridge), we cleared the drain in the farm track under the bridge. This is taking a lot of water flowing from the adjacent field on the down side down the farm track. We noted the condition of the up side high mileage wing wall of bridge 20 is very poor (large crack) and water is dripping through the deck beams.
Similarly at bridge 19 (New Farmers Accommodation Bridge) we improved the flow of water under the bridge. Here we noted two missing bricks (one each in both low mileage wing walls) which we will replace next week. We didn't take any spare bricks with us today.
Another brick in the wall required (bridge 19). However, Pink Floyd not with us today! |
At Hayles Abbey Halt bridge (17) we measured up the broken high mileage up side coping stone. Unfortunately we could not find any of that size in the piles at Winchcombe yard, so this will be another repair job.
Fortunately weather was reasonable; rain had stopped before we arrived at Winchcombe. But the effects of a week with several very wet days was obvious; some of the streams were flowing fast. So too were some of the cess drains, however, some (like 19B) are still dry!
The wet conditions under bridge 19. |
Thursday 24th November
All seven members of the team attending today, but one (our plant operator) was booked for the telehandler refresher course; so only six of us working on our tasks.
We split into two teams of three. The first team spent most of the day in Winchcombe yard attempting to map out what grills are connected to what drains and where they eventually go to. This is in connection with a new concrete apron at the low mileage end of the C&W building. Some 'non-railway' sewers were identified; plus using die tracing we confirmed that water from the surface drain in Churchward House yard; plus those from the grills in the main yard do eventually exit into the down side ditch. This exit is marked with a blue top post; it is about 15 yards upstream from the point where the ditch enters a pipe which runs into the River Isbourne, on the upstream (down side) of the river bridge. We also found a chamber near the end of the old goods shed part of C&W which also is likely to be connected to this exit. Unable to trace this one; as currently the scaffolding for the C&W roof repairs prevent the cover being removed.
The second team attended to various odd jobs identified in the past couple of weeks on the culverts and cross drains between Chicken Curve and Didbrook. We removed the bits of cement bag acting as weather-protection at 20B and replaced the covers with grills at 19B up side.
At 19B up side, one of the old covers was just an unreinforced slab; however the other, larger, old cover was reinforced and took some breaking up. We removed the extensive grass bedding (badger maybe), below which was standing water containing a lot of silt, which we also removed. This work revealed that this chamber is actually quite deep, presumably to act as a silt trap at this point. The water level was below the level of the pipes, so no water was flowing through.
We replaced 2 missing bricks in the wing walls at bridge 19 (New Farmers Accommodation Bridge) and reseated a third which we noticed was loose.
Spot the reseated brick (bridge 19). [Photo by Dave] |
We repaired the broken coping stone at bridge 17 - a replacement complete stone would look a bit better, but none of that size in stock.
Repaired coping on high mileage up side at Hayles Abbey bridge. [Photo by Dave] |
We did the rebuilding at 16C down side low mileage wing wall. The by now heavy ran meant our master bricklayer was struggling to achieve a result here which met his high standards! Will need to return to clear up the newly-laid bricks smeared with mortar.
Rebuilding the down side wing wall at 16C - despite the sign says 16A (the signs were made before what is now 16A and 16B were discovered. Making new signs is on our 'To Do' list!) [Photo by Dave] |
Heavy rain forced all work to cease around 2.30pm!
Thursday 1st December
Six of the team attending on a very misty/foggy day. A new novel excuse from the 7th member, he had broken his unbreakable glasses.
Again we split into two teams of three.
Team A initially headed for Southam Lane to rectify three down side cess chambers where either lids had been knocked into the chamber or the whole ring structure had been shifted. We used blue plastic mesh covers temporarily as the lifting straps were on the truck team B had.
Southam Lane in the fog - the bridge is just visible. |
Then back to Working Lane to continue internal visual inspections of culverts/cross drains. Four completed – culvert 24A and cross drains 25B, 25C, 27A. Really this is only 3 and half as the inlet to 25C is outside of the railway boundary beyond a sturdy fence.
Team B took the LWB Transit van for a longer run, which gave the batteries a good charge. The main objective was to deliver the flail for a service at Blockley (south east of Broadway). They then returned to Toddington and completed the minor repairs to the brickwork of culverts/cross drains 16B, 17A and 19B. So on next year's internal inspections some of the recommended actions can be crossed off as complete. Also returned to 16C to complete the pointing and to tidy up using a wire brush to achieve a neat finish. (See last week’s report above.)
Pub with No Beer
A railway theme beer festival - now that is a splendid idea! |
Since the finish of the regular passenger trains at the end of October, and thus the Coffee Pot on Winchcombe Station not opening, we now retire to the Churchward House mess room for our end of day cuppa. This does mean that someone has to remember to bring in some milk! Whilst supping our tea, we look longingly at the board in the photo above, dreaming of a pint of one or more of the advertised drinks!
No comments:
Post a Comment