Monday 13 January
Not all goodbye's are sad, this morning's was no exception as the old container left Stanton for the breakers yard. The main thrust for today was getting some water drained off the crest on the down side at Hunting Butts. The crest drainage needs to be refurbished before the new anti-vandal fencing is erected and the ground needs to be a bit dryer to get the excavator in to clear the ditches. On the way to Cheltenham the gang dropped in at Gotherington to measure up on the land slip, not good news it's still on the move.
|
Goodbye rusty container 😊 |
Down at Gotherington levels on the slip show that it is still on the move.
|
Roger and Nigel setting up (Photo: Dave) |
|
Slip fracture (Photo: Dave) |
|
Level from the rail head (Photo: Dave) |
|
Slip face (Photo: Dave) |
|
Roger and Nigel taking levels (Photo: Dave) |
|
Toe drain manhole metal cover disappeared |
Next stop was Hunting Butts to try and get some water from the crest before more rain arrived, plus do some CCTV and make a couple of chambers safe with new covers
|
Dave, Roger and Nigel digging a grip down the slope |
|
Generator and tools transported up to site |
|
Hunting Butts down side crest (Photo: Dave) |
|
Chamber 2, flail damaged lids and top ring (Photo: Dave) |
|
Grille lids fitted and mangled ring removed |
|
Getting into the boggy area |
|
Access gate, no pipe has been found under the entrance track |
|
Rodding eye has been bashed about a bit (Photo: Dave) |
We found a blue plastic pipe running at an angle down the slope, could this be a drain form the crest? not quite, it ran half way up the slope 😕
|
Rodding the blue pipe |
The CCTV showed that the pipe was dead end
The gang looking for the pipe end, it was covered with brash...
|
It's in here somewhere |
|
End of the plastic pipe |
|
CCTV on the crest drain pipe |
The pipe is in poor condition close to the chamber, but get's better further along.
The crest ditch area had dried out a bit when we left
|
Water draining down to the cess |
|
The gang on the way back to the truck |
Thursday 16 January
It turned out to be a a day of two halves today, the morning was bright but then the rain and wind came driving across. We managed to do some surveys and checks on work in progress before beating a retreat from the elements.
First stop Winchcombe cutting to have a look at the up side slip area. Some temporary drainage is being installed to divert water from the crest.
|
Winchcombe Cutting, the tree heads towards the horizontal |
|
The slip toe is creeping over the chamber in the cess |
|
Contractors excavating to install temporary pipework |
|
Michael inspecting the new pipes |
|
Pipes will be passed into the cess chambers |
|
Winchcombe Cutting up side slip area |
The flooding from the adjoining fields over the down side crest has been causing us some concern. There is a crest drain along from the tunnel that routes a couple of streams down to the cess, or so we thought. As usual, another mystery was uncovered, the 24" crest drain runs on towards the Greet Road bridge, to a destination unknown as yet.
|
Presumed end chamber on the down side crest one of the lids has cracked, they aren't reinforced |
|
Andrew and Dieh clearing around the last chamber |
|
Removing the broken lid proved a challenge, it was heavy and determined to fall into the hole |
|
24" crest pipe heading from the tunnel direction |
|
24" pipe and contents heading towards the bridge |
|
225mm pipe in from the field and 6" pie down to the cess drains crossing the chamber |
|
24" pipe heading towards the bridge |
|
Cess drain is running a 9" pipe |
|
Andrew and Dieh replace the cess lids |
|
24" pipe running a few inches below the surface |
|
Micheal uncovering the 24" pipe |
|
Second field stream entering the crest drain |
|
End of the crest drain up near the tunnel portal |
|
The gang erecting safety fence around the end chamber |
The destination of the 24" crest drain isn't clear, it could possibly run into the stream that runs down the back of Winchcombe yard.
|
Stream entry chamber opposite the station entrance |
|
Inside the stream chamber, no 24" pipe |
The River Isbourne erosion control works have been suspended for a while, the river has become too unpredictable with constant rain.
|
River levels this week |
|
Progress on the down side of the River Isbourne |
The slip at Bridge 37 at Gotherington is still moving, a check of the levels today show a drop in the last 3 days.
|
Gotherington Bridge 37 up side slip face |
|
Andrew near the slip face for perspective |
|
Slip toe |
|
Another crack and ponding water on the slope |
|
Slip face crumbling |
|
Crack at the south end |
|
Slip area, view from the toe |
The manhole on the toe drain has almost disappeared, just the edge of the concrete cover is visible. The toe has drifted by around 200 mm in 3 days.
|
Concrete manhole ring, just visible |
|
Toe drain is vertical as the move moves |
Last stop was to have a look at the drainage pits on the viaduct. By this time the wind was such that it was difficult to stand. The concrete covers have been cast and they are starting to be placed on the pits that have been cleared.
|
Stanway Viaduct, drainage pit excavations |
|
Cast slab ready to be placed on the pit |
|
Slab fixed in place |
Are there any views on whether the Gotherington slip is likely to have a serious effect on the safety of the line? The last thing that's needed is another line closure to effect repairs!
ReplyDeleteSigh, that Gotherington slip is looking really ugly; I suspect it's going to take a Chicken Curve-sized repair. I hope the line won't be separated in two at any point. I wonder why it has just failed now?
ReplyDeleteAre there more potential trouble-spots along the line? I know there was a history of prior issues at Chicken Curve, but I don't know if Gotherington had a history too. If there are, Broadway-type repair(s) there might be a wise move; the GWSR would probably have to delay other projects as a result, but better that than another one of these!
Oh well, when they are all fixed, you all will have a roadbed that should give many years of service.
Noel