Friday, 12 September 2025

Season of Plenty

Thursday 11th September

Certainly autumn now, the season of plenty. Another day when the weather turned out better than forecast; the showers held off until lunchtime and then were not that heavy or thundery. A strong breeze kept the temperature down, but still warm enough for physical work outside. A team of eight in attendance, initially splitting into a group of two and a group of six.

The pair were Jonathan and Polly, their first task was the removal of old fencing wire from the very end of the low mileage down side toe ditch which leads into the River Isbourne. To avoid a long walk along the ditch, and the climb down from the railway; they accessed the ditch using the old gate from the B4632 roadside. They took the recovered debris back to the metal skip in Winchcombe Yard; then collected bricklaying tools plus some sand, cement and water to head to Stanton.

The gate by the roadside with the pipe under the road just visible bottom left. [Photo by Jonathan]

Cleared ditch flowing slowly down to the Isbourne.[Photo by Jonathan]

Meanwhile the group of six travelled to Stanton Yard; and then splitting further. Roger and Martin accessed the line at Stanton Field bridge (7); then proceeded to clear vegetation from around the cess chambers on both sides of the line north to Laverton foot crossing. They also cleared around the mileposts, including 7¼, which is just north of the foot crossing. This one is set well back from the vacant trackbed where the up line was; so encroaching vegetation can soon obstruct it.
Milepost 7¼ no longer hiding in the undergrowth. [Photo by Roger]
Looking north from culvert 7A towards Stanton Fields bridge (7); cleared cess chamber on left. Note how the vegetation has grown on the up side bank on the left. The whole length between bridges 8 and 7 was flailed back in April. 

Nigel, Martin, Andrew and Ian tackled the vegetation clearance at syphon culvert 7A. There was only a dribble of water flowing through this, and the outlet of this was dry. This enabled the removal of the silt covering the base; and some of that in the outlet ditch back to the boundary fence. Usually there is standing water over 2 feet deep here. Once Polly and Jonathan arrived with the bricklaying tools and materials; they set to work filling the cracks around the outlet bore and in the wing and headwalls of the outlet.

Crack around the outlet bore of 7A, previous repair stopped at the normal waterline. With no water in the outlet ditch; Polly was able to re-point right round the bore.

Whilst Andrew completed the visual inspection of 7A; Nigel, Dave, Martin, Roger and Ian continued with vegetation clearance. They completed all the cess chambers between bridge 7 and bridge 10; the access paths to both sides of Stanton Aqueduct, the down side slip marker posts under the aqueduct, around the mileposts and the small chambers on the down side cutting crest high mileage of bridge 10.

A cess chamber in need of attention; probably hit by a vehicle loading or unloading ballast at Stanton. We will have to raise the height of this to make it more visible.

The first rain shower arrived conveniently at lunch time; so no use of deckchairs today. Fortunately with three vehicles, there was a reasonable amount of space for all eight of us to eat in the dry. After lunch, the combined team headed down the line towards Stanway, clearing the cess chambers and then culvert 11A and cross drain 11B. This enabled visual inspections of these two structures; the small stream which flows through 11A was just a trickle; the cess drains were dry, so too was 11B.

Roger cutting an access down to the main entry of culvert 11A.

Another rain shower temporarily halted work; so we decided to leave clearing and inspecting culvert 11C until next week. Of course, as soon as we packed up and headed back to Winchcombe, the sun came out!

Smiles from some of the team (Ian on right) as it is the end of todays work so head back to the trucks and off to Winchcombe for a cup of tea in the cafe.

Wildlife report: An early sighting at Stanton were some red admiral butterflies, with a few cabbage whites seen later. As befits autumn, the season of plenty, the abundance of fruit was very obvious. All the pear trees at Stanton were heavy with fruit; some still rock hard as they are perry pears, but others are eaters and were just ripening. Juicy but very dry was the taste verdict of one team member. Still plenty of blackberries on the brambles, but now past their best. The remaining berries are smaller and not so sweet. Also well past their peak are the damsons, most had fallen off the trees and were lying on the ground. In contrast, although now ripe the majority of sloes were still on the trees. In the brush we noted several wild roses with plenty of hips, plus a few asparagus plants which had fully grown into tall ferns. Just a few flowers remain; including cornflowers and a few daisies.

Red admiral.

A laden Stanton pear tree.


Friday, 5 September 2025

Flowing again

Thursday 4th September

Almost all of the team attended on what initially looked like it would be the wettest day we have worked for a long time.

Ian, Martin and Jonathan took on the completion of the clearance of the down side low mileage toe ditch at the River Isbourne bridge (21A). This is the ditch that runs alongside the Winchcombe Industrial estate, with Winchcombe Reclamation being the immediate adjoining premises. They finished the vegetation clearance right up to the B4632 main road. This revealed an old gate from the roadside, however it is immediately above the ditch, so of no use for access with mechanical plant. The group cleared the two sections of ditch that was obstructed with soil; and also removed an obstruction at the end of the (non railway) culvert that runs under the B4632 road. The result of this was that water began to flow down the ditch, although slowly. Apart from the River Isbourne, this was the only flowing water the team encountered today.

The old gate is just visible above where the toe ditch ends. [Photo by Jonathan]
With the exit from the culvert under the road cleared, water begins flowing down the ditch. [Photo by Jonathan]

Ian (l) and Martin showing how shallow the River Isbourne still is. [Photo by Jonathan]

An afternoon task was the cataloguing of our stock of tubes for the manufacture of safety rails and markers. Some of this is bespoke handrail tube, but most of recycled scaffold poles.

The other seven attendees undertook the culvert and cross drain visual inspections and clearance for the day. They travelled north to Little Buckland; where they split into to teams. Dave, Nigel and Peter headed south to deal with cross drains 5D and 6A at Laverton; also clearing the up side toe drain chambers north of bridge 6. 

Nigel on the brushcutter clears around the 6A exit chamber whilst Peter removes a sapling with the loppers. [Photo by Dave] 

The end result - chamber lids exposed and access cleared.

Roger, John, Polly and Andrew headed north to Peasebrook to attend to cross drain 3A. On the way they cleared around the now disused field access on the down side – this to ensure we can safely turn our vehicles here. This reduces the distance travelled in reverse between Little Buckland and Peasebrook. Next item for clearing was the length of the down side toe ditch between cross drain 5B and the northern most foot crossing. Even after the rain over the past few days; there was no water in this ditch.

Adhering to our confined spaces procedure, Roger enters the exit chamber of 3A whilst John holds the gas detection unit.
John tidying around the down side of the northern most foot crossing at Little Buckland. 

All seven then met up at Meadow Lane bridge for lunch – slightly extended to await the passing of a short but heavy shower of rain. After lunch the final structure for clearing and inspecting was the syphon cross drain 6C, which is just north of Stanton Fields bridge (7).
The inspection and clearing team (well 5 out of the 7) finish off and start packing up at 6C. Stanton Fields bridge 7 in background.

Wildlife report: No interesting mammal sightings today. At Little Buckland we noted a buzzard hunting over the adjacent field, so probably there are some small mammals there. The work at Stanton Fields disturbed a family of crows. The most numerous creatures we encountered were arachnids. Every chamber we inspected seemed to have a resident spider or two. 

Apologies to anyone suffering from Arachnophobia. 

Friday, 29 August 2025

Last of the Summer Days

Thursday 28th August

An almost full attendance on the last Thursday of (metrological) summer. Ten of the team enjoyed the late summer sun in the morning, but with a few rain showers and a chilling breeze, there was certainly an autumnal feeling to the day.

Two groups were in action. The larger group of six headed for Little Buckland. Here Ian and Martin trimmed the access ramp from the road. Meanwhile, Polly, Peter, Nigel and Andrew took the tipper transit (well three did – one walked) a little further north to place some spent ballast and other infill on top of the section of twinwall pipe we laid in the down side toe ditch a little while ago. (Link

Twinwall pipe in toe ditch now buried. (This stops sunshine degrading the plastic).

All six of the group then combined to start our annual programme of clearance and visual inspections of the culverts and cross drains. The honour of the first candidate this year fell to cross drain 5A. This required very little in the way of clearance; as we had visited this four weeks ago to improve the outflow ditch. Our report from a year ago contained the observations “flowing well” and “water too deep to photograph through the bore”. What a change this year – no water at all, not even any damp spots in the inlet or outlet ditches.

Inlet of 5A showing a tide mark when in wet periods water pools as the bottom of the twinwall pipe is several inches above the base.
Polly (l) and Peter acknowledge the approaching up train at Little Buckland bridge. End of summer - so with advance preparation we have a loco fitted with snow ploughs! (26043, one time D5343, looking splendid after its major overhaul and repaint.)

So
then a swift move on to cross drain 5B. This did need more vegetation clearance on the up (outlet) side. Another task here was the backfilling of the up side headwall with more of the spent ballast and spoil we had brought. We determined the safest and quickest method was to shovel the material from the bed of the truck into buckets; then to use a chain gang to pass the buckets over the running line and down the embankment for careful emptying in the voids. We completed this well within the 45 minute gap between the down train passing and the next up train departing Toddington. Filling the gaps behind headwalls and the tops of wing walls reduces the risk to us or other lineside workers of broken ankles or other injures from trapping feet in the gap.
Three men went to mow - left to right Ian on brushcutter, Nigel on hedge trimmer and Peter on rake. 5B up side outlet.

Clearance of the down side inlet of 5B was much less demanding. This was part of the major works undertaken last autumn and winter in conjunction with the adjoining land owner. Vegetation clearance here, and in the toe ditch between 5A and 5B was very straightforward. It was mainly grass with just a few lengths of bramble.

5A to 5B down side toe ditch -one year of growth but mainly grass.

The other group had a much more challenging clearance operation. This was to continue with the exposure of the down side toe ditch that runs back from the River Isbourne to the B4632 road bridge at Winchcombe. The fab four undertaking this were Roger, Dave, John and Jonathan. None of the team can remember when this ditch was last cleared – so not surprisingly the vegetation was dense. Even after this warm dry summer, in places this ditch was damp and in others the mud was quite deep. With out the exceptional dry summer this year, clearing this ditch would have been very difficult. In one spot there is a very deep puddle – possibly this is fed by a spring or from the adjoining industrial estate. We know that this ditch flows very strongly during wet periods and when the River Isbourne is in flood. Consequently we need to ensure that water is flowing out to the river without impediment to alleviate the effects of flooding on the industrial estate. Jonathan spent quite some time ensuring the length of twinwall pipe that takes the outlet of the ditch through the gabions beside the river was clear. During the afternoon, our fencing and clearance contractor visited, to assess how much of the down side embankment is accessible with his robot flail. What the robot can not handle will have to be dealt with by our colleagues in the Lineside Clearance team.

Looking towards the pipe under the river gabions. [Photo by Dave]
The 'coalface' - now about 30 yards away from the B4632 road. [Photo by Dave]
John rakes cut material from the floor of the ditch. [Photo by Dave]
A ring of sunlight highlights one of the team clearing the ditch. [Photo by Dave] 

Wildlife report: The group at Little Buckland collectively spotted a trio of mammals – rabbit, hare and weasel. Or maybe the later was a stoat – it is difficult to tell these apart particularity when only glimpsed. Stoats are larger, they also have a longer tail with a black tip. Overhead a pair of buzzards were heard then seen – whilst robins and a wren were spotted in the boundary hedges. Loads of blackberries in the hedges, some now very large in size and delicious; plus a few sloes (not so delicious!) On the down side embankment near cross drain 5B is an apple tree, probably a Bramley. Some of the team took some of the fruit home with them. The Isbourne contingent spotted a sparrowhawk swooping over the embankment – no doubt taking advantage of the cleared section to spot prey.

Blackberries in the lineside hedge at Little Buckland.

Does this count as wildlife? A rat mounted on the lamp iron of the McRat 26043 - passing over the Isbourne bridge approaching Winchcombe.

Friday, 22 August 2025

Another day on the River

Thursday 21st August

A late change of plan enabled all nine volunteers to spend another day working on the River Isbourne bridge (21A).

Polly, Nigel and Martin focused on improving the ‘homemade’ steps that lead down from the up side vacant trackbed to the bridge parapet. This involved some chain saw use to remove as much as possible of two tree stumps. They also added two new steps; dug out the bank and added some spent ballast to make the steps level.

Polly, Nigel and Martin working on the up side steps.
The results of the improvement.

Dave and Ian concentrated on the down side low mileage toe ditch. This runs from the B4632 road bridge past the back of the industrial estate. It was very overgrown; but still damp in places which shows that water does flow down to the river The twinwall pipe under the right bank gabions was checked for obstructions. In the river bed some of the silt build up was removed to ensure a channel for the discharge from this pipe to flow away. They cut an access to the ditch; and then began clearing the ditch. This was slow work – by the end of the we think only a quarter of the distance to the road was cleared.
Ian inspecting the twinwall pipe under the gabion. [Photo by Dave]

The toe ditch looking towards the B4632. [Photo by Dave]
Dave surveys the plants growing on the single bank in the river bed. Note the channel for the flow right by the gabions. 

The rest of the group (Jonathan, John, Peter and Andrew) worked on the downstream, up side of the bridge. More use of restraining harnesses attached to the parapet safety rails enabled the headwall to be cleared of moss and other items of vegetation. By working on just below the gabions (the water level is still very low) they removed lots of Himalayan balsam and other vegetation by the wing walls. Peter and Andrew removed yet more Himalayan balsam and some willow trees from the down stream banks. Jonathan dug out some of the silt that had built up where the vegetation has taken hold. John was on stamping duty, treading on the flowers and seed heads of the cut balsam. Hopefully this will reduce the spread of this plant.
Up side (down stream) portal of the bridge. Jonathan hiding behind the grass whilst dredging the silt.
Close up of the up side high mileage wing wall. As this is the north side of the bridge the vegetation stays damper; so the mortar joints are not as good as those on the down side which gets more sunshine.

Wildlife report:
Early on we spotted a kingfisher on the down (upstream) side of the Isbourne; obviously there is good fishing here. Lots of ripening blackberries and sloes on the embankment side. And of course plenty of Himalayan balsam. That does seem to attract lots of bees. On the oak tree (down side, low mileage of the river) we noted lots of galls, each containing a larva of the common spangle gall wasp.
Galls on oak tree. [Photo by Dave]

Friday, 15 August 2025

Seven Up - again

Thursday 14th August

Another work day with seven of the team attending – but a slightly different seven than last week. (Jonathan, Andrew, Nigel, Martin, Polly, Stuart, Peter). The others were either on holiday, doing paid work or had family commitments.

The River Isbourne bridge, structure number BU21A, was the work site for the day.

On the up (Malvern) side; the task was to clear the access from the vacant track bed down to the headwall; then on the safe side of the safety rails down the two wing walls to the stream. The dry conditions making this a much less hazardous task.

On the down (Cotswold) side, the main task was to make the steps leading down to the headwall safe. These were constructed by a contractor during the Isbourne flood works a few years ago; but due to Covid-19 were never fully completed. We used a mix of spent ballast and some smaller spoil to level out all of the 29 steps. Jonathan used the telehandler to transport this material from the PW stockpile in the up side yard at Winchcombe. With careful direction he positioned the telehandler by the Winchcombe up advanced starting signal, then extended the boom to enable the spoil to be deposited on the down side of the running line. This was undertaken under a line block agreed with the Winchcombe signaller, between the empty down train to Cheltenham and the first up passenger train. Nigel, Andrew, Peter and Martin undertook the shovelling and barrowing of the spoil to the steps – assisted by gravity! Stuart attended to the ramming and filling of the steps and Polly constructed some shuttering to form an extra step at the bottom. Four telehandler loads of spoil was more than sufficient for the steps, we spread the extra between the buffer stops of the first down side siding and the top of the steps.

A dust cloud arises as a load of spoil is deposited as close to the down side steps as possible.
Stuart ensures the infill is packed in level.
Looking up - three of the shovelling team take a breather.
The bottom part of the steps completed.

Meanwhile, Jonathan donned a safety harness and suitably attached to the safety rails on the down side headwall removed the bramble and other vegetation that was growing there.

Clipped to the safety rail, Jonathan takes a break from vegetation removal. In the background Stuart finishes off the step infill.

After lunch, attention turned to the vegetation growing on the down side wing walls. Working both from above and below (but not simultaneously!); we removed creepers and moss from the mortar joints. The moss being bone dry came away easily with a long handled hoe. On the high mileage wing wall we removed several inches of soil – with a lot of bramble roots embedded within. The copings of both the low and high mileage wing walls are now exposed – and all the mortar joints are in good order.

Low mileage down side wing wall after clearing.
The now exposed copings of the high mileage down side wing wall.  

From the river the down side looks a lot neater - but not finished. The remaining bushes above the bridge arch require removal. The low level of the river is obvious; Andrew is walking on the lowest tier of gabions, normally these are under water. [Photo by Jonathan]
From above the down side steps are now unmissable.

Wildlife report:
One brown trout was observed in the River Isbourne; but with some of us wading in the stream, it made a hasty retreat. Like a lot of water courses in the Midlands, there is a significant growth of Himalayan balsam. Whilst this has pretty pink flower heads, it is a non-native invasive species. However, completely eradicating it is almost impossible. Cutting the stems spreads the seed, so encourages further growth. The only effective way of dealing with is to pull the plant out by the roots, then to stamp on the flowers and seed heads. This prevents the seed from germinating. All in all a very laborious and time consuming process -so we only remove plants that are obstructing the water flow.

Friday, 8 August 2025

Squeeze Avoided

Thursday 7th August

It was a good thing that only seven of the team attended today. If all the team turn up for work we need a minimum of three vehicles to convey us and our tools to the work sites. Today, only two vehicles were available; S&T and C&M were using the other two. Roger, Jonathan, Dave, Nigel, Ian, Martin and Peter were the magnificent seven; the blue tail-lift Transit and the Isuzu their stallions!

First stop was Two Hedges Road, or more precisely the down side high mileage vehicle track and footpath alongside the former Bonsai World site. The task here was to reinstate the fence alongside the site – removed to allow the new stream inlet pipe to be fitted. The new inlet apron with integral bars looks very smart. This type of collector could in several other locations to stop debris entering the drains.

Many hands help make fencing jobs easier. [Photo by Dave]
The reinstated fence by the gate leading from the vehicle track/footpath into the adjoining field. [Photo by Dave]
 

After coffee the team moved to the ditch behind Willow Drive mobile home site at Woodmancote. This was to finish vegetation clearance of the toe ditch on the low mileage side of culvert 38A; and to cut an access gap down the embankment near to Station Road bridge. We cleared the debris from the other week and dug out the high spots in the ditch. Water is flowing more freely now, further digging may be required if the winter storms do not wash more of the silt out. We also uncovered a third salt glazed pipe which could be an original field drain at the high mileage end of the toe drain. We cleared as much silt out of the pipes as possible. There is a lots of detritus still there as we had no room to put it in vehicles to take back to Winchcombe. A strange find uncovered was what appears to be a "heritage cement fibre pipe" lying in the undergrowth.

Third SGP pipe feeding the ditch near Station Road. [Photo by Roger]
After the rain over the past week, there is flowing water in the toe ditch. [Photo by Dave]

We returned to Winchcombe for late lunch and then some of us went on the train to Broadway to undertake a visual survey of the culverts and cross drains that we will be clearing and visual inspecting next month. The remainder of the team headed for the Rive Isbourne bridge to meet with Peter and John (S) from the Bridges team to discuss further clearance of the wing walls there.
Down side low mileage wing wall of the River Isbourne bridge; moss on the mortar to be removed. [Photo by Jonathan]

Finally, over afternoon tea, we discussed the exhibit that Ian is coordinating for the Railway 200 event at the end of September.

Wildlife report: Again the highlight sighting was from the River Isbourne, but this time in the river. Three brown trout swimming upstream. Also a large number of dragon flies. And lots of Himalayan Balsam,  which is a non-native invasive plant. However total eradication is very labour intensive.