With both Christmas Day and New Year’s Day this winter falling on Thursdays; to avoid loosing two working days, by a majority democratic
decision, the team decided on a Friday workday for one week. Maybe
this was a desire to work off some the excesses of Christmas!
Thursday 1st January
However, for one of our team, Friday
is a paid work day. So, in his role as vehicle and plant maintenance,
Jonathan attended on New Year’s Day. With all the vehicles in the
yard, this was an ideal opportunity to give them all a good external
wash and for some an internal clean.
 |
| The white Ranger gets a foam snow wash. Overnight there was some real snow. [Photo by Jonathan] |
 |
| Four clean vehicles - a rare sight! [Photo by Jonathan] |
Friday 2nd January
So to break the ice on 2026
(literarily!) seven of the team put in a full day, with help for two
others who had other commitments in the afternoon.
We tried our best to keep the three
vehicles we used clean – participially be not going tack side and
cleaning boots before climbing board. However, the muddy puddles in
Winchcombe yard and on on the roads can not be avoided.
All the team headed for Toddington to
park in the station car park. Usually we started with a tea/coffee
break to warm up – and consume some festive edibles. Then down to
work.
Nigel and Peter cleared the vegetation
on the top of the down (Cotswold) side cutting on the low mileage of
Stowe Road Bridge. This was to enable a survey to determine where to
cut a new drainage ditch. This is to catch the field and road run off;
routing this to new French drain (or maybe a pipe) to take the water
to the down side cess well away from the bridge. Currently in very
wet periods, water cascades under the side arch of the bridge,
washing down large amounts of silt. A lot of this ends up on the
cess, exactly where locos are coupled or uncoupled and in the cess
drains. And sometime the water flows across Stowe Road and flooding into Station Cottages.
Dave, Martin, John and Phil set to
work clearing the entrance on the up (Malvern) side cutting crest and
then continued along the crest fence line all the way to Stanway
Viaduct. There is a crest drain pipe for half of this length; with
some new(ish) chambers towards the viaduct. Nigel joined the Stanway
bound group, clearing around the cess chambers on both sides of the
line.
 |
The
'new' crest drain pipe was flowing slowly so showing why crest drains
are so important in keeping cutting sides dry and stable. [Photo by Dave]
 | | The
north end of Toddington North cutting where it falls away to the
embankment leading to Stanway viaduct is a very photogenic spot. Even
with just a stationary line of goods wagons on the siding. One of the
'new' crest drain chambers in the foreground. [Photo by Dave] |
|
 |
| The Stanway vegetation cutting group are just visible in the distance.
The frost on the sleepers in the shadow of the bridge lasted all day. |
Meanwhile Dee and Andrew began
excavating the deposited silt from around the first down side cess
chamber by the bridge pier. A tricky job here as there are four S&T
cables which run either over the top of the chamber or actually
through it. Peter and Phil later joined; enabling the removal of the
metal mesh chamber lid and thus use of a grab to remove the
accumulated silt from the chamber. Also the lid removed, we were able
to finalise a plan for the improvements. This will be to raise the
chamber by one brick course, either side of the cable, then to
install a GRP chamber ring and blue mesh lid to raise the height of
the chamber. Also the plan is to construct a small retaining wall
behind the chamber – both of these measures should reduce the
amount of silt entering the cess drain. And make for a less muddy
path under the bridge to the end of the platform for the train crews.
 |
| The cess chamber cleared of silt and the inverted U channels over the top of the S&T cables. |
 |
| Checking for size and height of the planned rebuilt. |
 |
| Metal grid lid removed. |
 |
| Phil, Peter, Dee and John on the chain gang using the grab to remove silt from the chamber and to dispose where it will not flow back in. |
Whilst we were there, we removed a
long redundant fence post adjacent to the bridge pier. It obviously
dates from the time when a fence extended across the track bed under
the bridge when operations were only to the south of Toddington.
Whoever installed that post intended it to last – no amount of
digging or hammering would shift it. So when Ian arrived (see below),
he was promptly dispatched to fetch a chain saw to cut the post off.
There is a similar post on the up side of the line – we shall
remove another day!
 |
| John, Dee and Peter attempt excavation of the fence post. Note the deployed red flags, however, no stock movements took place. |
 |
| The sawn off fence post stump - well ensconced in a lump of solid concrete. |
 |
| Temporary covers in place. |
Wildlife report:
On his way into
Winchcombe, Ian cam across an injured tawny owl sitting in the middle
of the road. He
stopped to investigate, and as the bird was too injured to resist, he
put it in the bot of his car. At Winchcombe we found a cardboard box
and some paper towels to make a more comfortable bed/nest; and then
set about finding a suitable rescue centre to take the casualty to. This turned out to be almost back to Worcester – so a bit of a journey, hence Ian’s later
arrival at Toddington. We did save him an iced bun (Ian that is, not the owl). |
| The injured tawny owl. |
Other
more mundane observations at Winchcombe were our resident robin in
the wooden shed and a very low flying male pheasant who came to
investigate the owl. Observations from the top of the cutting sides
at Toddington included grey wagtails, Red Kites and buzzards. No sign of
any mammals, not surprisingly since the daytime maximum temperature
was only 3C (or 37.4
°F on the heritages scale).