Thursday 14th August
Another work day with seven of the team attending – but a slightly different seven than last week. (Jonathan, Andrew, Nigel, Martin, Polly, Stuart, Peter). The others were either on holiday, doing paid work or had family commitments.
The River Isbourne bridge, structure number BU21A, was the work site for the day.
On the up (Malvern) side; the task was to clear the access from the vacant track bed down to the headwall; then on the safe side of the safety rails down the two wing walls to the stream. The dry conditions making this a much less hazardous task.
On the down (Cotswold) side, the main task was to make the steps leading down to the headwall safe. These were constructed by a contractor during the Isbourne flood works a few years ago; but due to Covid-19 were never fully completed. We used a mix of spent ballast and some smaller spoil to level out all of the 29 steps. Jonathan used the telehandler to transport this material from the PW stockpile in the up side yard at Winchcombe. With careful direction he positioned the telehandler by the Winchcombe up advanced starting signal, then extended the boom to enable the spoil to be deposited on the down side of the running line. This was undertaken under a line block agreed with the Winchcombe signaller, between the empty down train to Cheltenham and the first up passenger train. Nigel, Andrew, Peter and Martin undertook the shovelling and barrowing of the spoil to the steps – assisted by gravity! Stuart attended to the ramming and filling of the steps and Polly constructed some shuttering to form an extra step at the bottom. Four telehandler loads of spoil was more than sufficient for the steps, we spread the extra between the buffer stops of the first down side siding and the top of the steps.
A dust cloud arises as a load of spoil is deposited as close to the down side steps as possible. |
Stuart ensures the infill is packed in level. |
Looking up - three of the shovelling team take a breather. |
The bottom part of the steps completed. |
Meanwhile, Jonathan donned a
safety harness and suitably attached to the safety rails on the down
side headwall removed the bramble and other vegetation that was
growing there.Clipped to the safety rail, Jonathan takes a break from vegetation removal. In the background Stuart finishes off the step infill.
After lunch, attention turned to the vegetation growing on the down side wing walls. Working both from above and below (but not simultaneously!); we removed creepers and moss from the mortar joints. The moss being bone dry came away easily with a long handled hoe. On the high mileage wing wall we removed several inches of soil – with a lot of bramble roots embedded within. The copings of both the low and high mileage wing walls are now exposed – and all the mortar joints are in good order.
Low mileage down side wing wall after clearing. |
The now exposed copings of the high mileage down side wing wall. |
From above the down side steps are now unmissable. |
Wildlife report: One brown trout was observed in the River Isbourne; but with some of us wading in the stream, it made a hasty retreat. Like a lot of water courses in the Midlands, there is a significant growth of Himalayan balsam. Whilst this has pretty pink flower heads, it is a non-native invasive species. However, completely eradicating it is almost impossible. Cutting the stems spreads the seed, so encourages further growth. The only effective way of dealing with is to pull the plant out by the roots, then to stamp on the flowers and seed heads. This prevents the seed from germinating. All in all a very laborious and time consuming process -so we only remove plants that are obstructing the water flow.